Changes between Version 79 and Version 80 of docs/CommissioningPlan


Ignore:
Timestamp:
01/18/21 14:53:10 (4 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan

    v79 v80  
    9494||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (days)'''||'''Category'''||'''LBTO Support'''||     
    9595||P2.0||[wiki:/docs/CommissioningPlan/P2.0 Installation of the SHARK-NIR at LBT platform]||Day||2(preparation) + 1(lift-off) + 1(contingency)||C1||Crew members' support for the preparation, lift-off, and installation of SHARK-NIR, crane operator (mountain bay, LBT platform), safety officer, working platform installed in front of the Gregorian focal-station SX, installation of electronics in LBTI/SHARK cabinet, check the installation document for more details||
    96 ||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Activating the instrument, basic check, initiate cryostat cool down]||Day||1||C2||support to verify the working of emergency button/stop?||
     96||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Activating the instrument, basic check, initiate cryostat cool down]||Day||1||C2||support to verify the working of emergency button/stop?, Testing the electronics and SW working of the knob (motor) controlling the cooling flow rate.||
    9797||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Instrument operability and functioning]||Day||1||C2||Liquid Nitrogen fill||
    9898||P2.3||[wiki:/docs/CommissioningPlan/P2.3 TCS communication test]||Day||1||C2||Authorize SHARK-NIR, connecting to ASM+LBTI AO system, able to send preset, receiving LBT telemetry (inc. the derotator trajectory) and details for the fitswriter, support from LBT SW team||