docs/CommissioningPlan
v72 v73 99 99 ||P2.4||[wiki:/docs/CommissioningPlan/P2.4 Align SHARK-NIR to the telescope]||Day||2+1||C2||working platform installed in front of the Gregorian focal-station SX, Mounting RR on the SX side. Support on running SOUL AO|| 100 100 ||P2.5||[wiki:/docs/CommissioningPlan/P2.5 SOUL AO system test]||Day||5||C2||working platform installed in front of the Gregorian focal-station SX, Mounting RR on the SX side. Support on running SOUL AO|| 101 ||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA ]||Day||5||C2 + C3||Mounting RR on the SX side. Support on running SOUL AO||101 ||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA(baseline, phase-diversity, Woll+DI-DBI+ARGOS swing-arm)]||Day||5+5||C2 + C3||Mounting RR on the SX side. Support on running SOUL AO|| 102 102 ||P2.xx||[wiki:/docs/CommissioningPlan/P2.xx Checking pointing offset between SHARK-NIR and SOUL-AO]||Day||3||C2||Mounting RR on the SX side. Support on running SOUL AO|| 103 103 ||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Looking for filter defects/effects/features+ Science detector calibrations repeat]||Day||2||C2||Mounting RR on the SX side. Support on running SOUL AO||