    8787||P1.8||[wiki:/docs/CommissioningPlan/P1.8 Verification of the internal alignment of the instrument]||Day||4||C1||optical bench needed in the cleanroom||
    8888||P1.9||[wiki:/docs/CommissioningPlan/P1.9 Science detector calibrations]||Day||1||C1||-||
    89 ||P1.10||[wiki:/docs/CommissioningPlan/P1.10 Testing of SCICAM imaging grabbing and ICE & SW compatibility between SHARK-NIR and SOULD-AO system]||Day||2||C1||LBTO SW support maybe required||
     89||P1.10||[wiki:/docs/CommissioningPlan/P1.10 Testing of SCICAM imaging grabbing and ICE & SW compatibility between SHARK-NIR and SOUL-AO system (Points of contact: Alfio + Fabio + Davide Ricci)]||Day||2||C1||LBTO SW support maybe required||
    9090||Total||Contigency of 1 day|| ||11+1=12|| || ||