    9393'''SHARK-NIR Location''' : LBT platform (Some of the activities may run in parallel). All daytime activities.
    9494||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (days)'''||'''Category'''||'''LBTO Support'''||     
    95 ||P2.0||[wiki:/docs/CommissioningPlan/P2.0 Installation of the SHARK-NIR at LBT platform]||Day||1 (preparation) + 1 (lift-off) + 1 (contigency)||C1||Crew members' support for the preparation, lift-off, and installation of SHARK-NIR, crane operator (mountain bay, LBT platform), safety officer, working platform installed infont of the gregorian focal-station SX, installation of electronics in LBTI/SHARK cabinet, check the installation document for more details||
     95||P2.0||[wiki:/docs/CommissioningPlan/P2.0 Installation of the SHARK-NIR at LBT platform]||Day||2(preparation) + 1(lift-off) + 1(contingency)||C1||Crew members' support for the preparation, lift-off, and installation of SHARK-NIR, crane operator (mountain bay, LBT platform), safety officer, working platform installed in front of the Gregorian focal-station SX, installation of electronics in LBTI/SHARK cabinet, check the installation document for more details||
    9696||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Activating the instrument, basic check, initiate cryostat cool down]||Day||1||C2||support to verify the working of emergency button/stop?||
    97 ||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Instrument operability and functioning]||Day||0.5||C2||Liquid Nitrogen fill||
    98 ||P2.3||[wiki:/docs/CommissioningPlan/P2.3 TCS communication test]||Day||0.5||C2||Authorise SHARK-NIR, connecting to ASM+LBTI AO system, able to send preset, receiving LBT telemetry (inc. the derotator trajectory) and details for the fitswriter, support from LBT SW team||
    99 ||P2.4||[wiki:/docs/CommissioningPlan/P2.4 Align SHARK-NIR to the telescope]||Day||1+1||C2||working platform installed in front of the gregorian focal-station SX, Mounting RR on the SX side. Support on running SOUL AO||
    100 ||P2.5||[wiki:/docs/CommissioningPlan/P2.5 SOUL AO system test]||Day||0.5||C2||working platform installed in front of the gregorian focal-station SX, Mounting RR on the SX side. Support on running SOUL AO||
    101 ||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA]||Day||0.5||C2 + C3||Mounting RR on the SX side. Support on running SOUL AO||
    102 ||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Looking for filter defects/effects/features+ Science detector calibrations repeat]||Day||0.5||C2||Mounting RR on the SX side. Support on running SOUL AO||
    103 ||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Flexure tests]||Day||2.5||C2 + C3||Mounting RR on the SX side. Support on running SOUL AO, the telescope need to move in elevation||
     97||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Instrument operability and functioning]||Day||1||C2||Liquid Nitrogen fill||
     98||P2.3||[wiki:/docs/CommissioningPlan/P2.3 TCS communication test]||Day||1||C2||Authorize SHARK-NIR, connecting to ASM+LBTI AO system, able to send preset, receiving LBT telemetry (inc. the derotator trajectory) and details for the fitswriter, support from LBT SW team||
     99||P2.4||[wiki:/docs/CommissioningPlan/P2.4 Align SHARK-NIR to the telescope]||Day||2+1||C2||working platform installed in front of the Gregorian focal-station SX, Mounting RR on the SX side. Support on running SOUL AO||
     100||P2.5||[wiki:/docs/CommissioningPlan/P2.5 SOUL AO system test]||Day||5||C2||working platform installed in front of the Gregorian focal-station SX, Mounting RR on the SX side. Support on running SOUL AO||
     101||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA]||Day||5||C2 + C3||Mounting RR on the SX side. Support on running SOUL AO||
     102||P2.xx||[wiki:/docs/CommissioningPlan/P2.xx Checking pointing offset between SHARK-NIR and SOUL-AO]||Day||3||C2||Mounting RR on the SX side. Support on running SOUL AO||
     103||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Looking for filter defects/effects/features+ Science detector calibrations repeat]||Day||2||C2||Mounting RR on the SX side. Support on running SOUL AO||
     104||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Flexure tests]||Day||3||C2 + C3||Mounting RR on the SX side. Support on running SOUL AO, the telescope need to move in elevation||
    104105||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Cryostat warm up check]||Day||2||C2||-||
    105 ||Total||Contigency included within || ||11 days || || Warming up time (of 2 days) not considered here ||
     106||Total||Contigency included within || ||27 days || || ||