    9494||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (days)'''||'''Category'''||'''LBTO Support'''||     
    9595||P2.0||[wiki:/docs/CommissioningPlan/P2.0 Installation of the SHARK-NIR at LBT platform]||Day||1 (preparation) + 1 (lift-off) + 1 (contigency)||C1||Crew members' support for the preparation, lift-off, and installation of SHARK-NIR, crane operator (mountain bay, LBT platform), safety officer, working platform installed infont of the gregorian focal-station SX, installation of electronics in LBTI/SHARK cabinet, check the installation document for more details||
    96 ||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Activating the instrument and testing instrument states & transitions]||Day||1||C2||support to verify the working of emergency button/stop||
     96||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Activating the instrument, basic check, initiate cryostat cool down]||Day||1||C2||support to verify the working of emergency button/stop?||
    9797||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Instrument operability and functioning]||Day||0.5||C2||Liquid Nitrogen fill||
    9898||P2.3||[wiki:/docs/CommissioningPlan/P2.3 TCS communication test]||Day||0.5||C2||Authorise SHARK-NIR, connecting to ASM+LBTI AO system, able to send preset, receiving LBT telemetry (inc. the derotator trajectory) and details for the fitswriter, support from LBT SW team||