Changes between Version 67 and Version 68 of docs/CommissioningPlan
- Timestamp:
- 01/15/21 10:23:04 (4 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan
v67 v68 87 87 ||P1.8||[wiki:/docs/CommissioningPlan/P1.8 Verification of the internal alignment of the instrument]||Day||4||C1||optical bench needed in the cleanroom|| 88 88 ||P1.9||[wiki:/docs/CommissioningPlan/P1.9 Science detector calibrations]||Day||1||C1||-|| 89 ||Total||Contigency of 1 day|| ||9+1=10|| || || 89 ||P1.10||[wiki:/docs/CommissioningPlan/P1.10 Testing of SCICAM imaging grabbing and ICE & SW compatibility between SHARK-NIR and SOULD-AO system]||Day||2||C1||LBTO SW support maybe required|| 90 ||Total||Contigency of 1 day|| ||11+1=12|| || || 90 91 91 92 === Phase 2 (Pre-commissioning)===