docs/CommissioningPlan
v61 v62 101 101 ||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Looking for filter defects/effects/features+ Science detector calibrations repeat]||Day||0.5||C2||Mounting RR on the SX side. Support on running SOUL AO|| 102 102 ||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Flexure tests]||Day||2.5||C2 + C3||Mounting RR on the SX side. Support on running SOUL AO, the telescope need to move in elevation|| 103 ||Total||Contigency included within || ||11 days || || || 103 ||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Cryostat warm up check]||Day||2||C2||-|| 104 ||Total||Contigency included within || ||11 days || || Warming up time (of 2 days) not considered here || 104 105 105 106