    130130 - you may see that there is some repetition in the activities. this needs to be sorted out eventually.
    131131 - the order of the activities may also be changed later.
     132 - the details of each of the activity (when you click on them individually) may not be complete and will be refined in time.
    132133
    133134To be added:
     
    142143Reminders:
    143144 - The space requirements at the mountain bay (@LBT) should be communicated to LBT at the earliest, along with the availability of crane operator, container moving tools, etc. Depending upon the month of the year, the mountain bay can be seriously booked (especially during July-October months due to summer shutdown).
    144  - The same is true for the clean room near the mountain bay. If we need access to the LBTO network in the clean room, there are some network ports. But we may need to tell them in advance (Talk to Florian Briegel for more info).
    145  - Note that if there is any ASM repair/activity scheduled in the clean room, preference is always for them and we will have to co-live or get after that.
     145 - The same is true for the cleanroom near the mountain bay. If we need access to the LBTO network in the cleanroom, there are some network ports. But we may need to tell them in advance (Talk to Florian Briegel for more info).
     146 - Note that if there is any ASM repair/activity scheduled in the cleanroom, preference is always for them and we will have to co-live or get after that.
    146147 - From the LINC-NIRVANA commissioning experience, it is always better to keep the tools associated with a particular alignment together, to avoid looking for it in all the boxes there. Also, there MUST be a **living inventory** wiki page where everyone should note down what is taken and kept in the box/container.
    147148 -  Space required by SHARK-NIR at 3L is already mentioned to JC and CV. Later, we may need to specify the exact area.