Changes between Version 52 and Version 53 of docs/CommissioningPlan
- Timestamp:
- 01/05/21 16:39:04 (4 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan
v52 v53 94 94 ||P2.0||[wiki:/docs/CommissioningPlan/P2.0 Installation of the SHARK-NIR at LBT platform]||Day||1 (preparation) + 1 (lift-off) + 1 (contigency)||C1||Crew members' support for the preparation, lift-off, and installation of SHARK-NIR, crane operator (mountain bay, LBT platform), safety officer, working platform installed infont of the gregorian focal-station SX, installation of electronics in LBTI/SHARK cabinet, check the installation document for more details|| 95 95 ||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Activating the instrument and testing instrument states & transitions]||Day||1||C2||support to verify the working of emergency button/stop|| 96 ||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Instrument operability and functioning]||Day||0.5||C2|| -||96 ||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Instrument operability and functioning]||Day||0.5||C2||Liquid Nitrogen fill|| 97 97 ||P2.3||[wiki:/docs/CommissioningPlan/P2.3 TCS communication test]||Day||0.5||C2||Authorise SHARK-NIR, connecting to ASM+LBTI AO system, able to send preset, receiving LBT telemetry (inc. the derotator trajectory) and details for the fitswriter, support from LBT SW team|| 98 98 ||P2.4||[wiki:/docs/CommissioningPlan/P2.4 Align SHARK-NIR to the telescope]||Day||1+1||C2||working platform installed in front of the gregorian focal-station SX, Mounting RR on the SX side. Support from LBTI/Arcetri on running SOUL AO|| … … 141 141 === Phase 4 (Science Verification / Early Science)=== 142 142 '''SHARK-NIR Location''' : LBT platform 143 ||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (mins)'''||'''Category'''||'''LBTO Support'''|| 144 ||P4.1||[wiki:/docs/CommissioningPlan/P4.1 x]||Night||10||C5||AO support|| 143 ||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (hours)'''||'''Category'''||'''LBTO Support'''|| 144 ||P4.1||[wiki:/docs/CommissioningPlan/P4.1 Direct imaging mode testing]||Night||3+||C4 + C6||AO support|| 145 ||P4.2||[wiki:/docs/CommissioningPlan/P4.2 Coronagraphic imaging + field stabilization mode testing]||Night||3+||C4 + C6||AO support|| 146 ||P4.3||[wiki:/docs/CommissioningPlan/P4.3 Coronagraphic imaging + pupil stabilization mode testing]||Night||3+||C4 + C6||AO support|| 147 ||P4.4||[wiki:/docs/CommissioningPlan/P4.4 Long-slit spectrograph mode testing]||Night||3+||C4 + C6||AO support|| 148 ||P4.5||[wiki:/docs/CommissioningPlan/P4.5 x]||Night||1||C4 + C6||AO support|| 149 ||P4.6||[wiki:/docs/CommissioningPlan/P4.6 x]||Night||1||C4 + C6||AO support|| 150 ||P4.7||[wiki:/docs/CommissioningPlan/P4.7 x]||Night||1||C4 + C6||AO support|| 151 ||P4.8||[wiki:/docs/CommissioningPlan/P4.8 x]||Night||1||C4 + C6||AO support|| 152 ||P4.9||[wiki:/docs/CommissioningPlan/P4.9 x]||Night||1||C4 + C6||AO support|| 153 145 154 146 155 Another Table with "science commissioning" to be added. More details soon.