    9494||P2.0||[wiki:/docs/CommissioningPlan/P2.0 Installation of the SHARK-NIR at LBT platform]||Day||1 (preparation) + 1 (lift-off) + 1 (contigency)||C1||Crew members' support for the preparation, lift-off, and installation of SHARK-NIR, crane operator (mountain bay, LBT platform), safety officer, working platform installed infont of the gregorian focal-station SX, installation of electronics in LBTI/SHARK cabinet, check the installation document for more details||
    9595||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Activating the instrument and testing instrument states & transitions]||Day||1||C2||support to verify the working of emergency button/stop||
    96 ||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Instrument operability and functioning]||Day||0.5||C2||-||
     96||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Instrument operability and functioning]||Day||0.5||C2||Liquid Nitrogen fill||
    9797||P2.3||[wiki:/docs/CommissioningPlan/P2.3 TCS communication test]||Day||0.5||C2||Authorise SHARK-NIR, connecting to ASM+LBTI AO system, able to send preset, receiving LBT telemetry (inc. the derotator trajectory) and details for the fitswriter, support from LBT SW team||
    9898||P2.4||[wiki:/docs/CommissioningPlan/P2.4 Align SHARK-NIR to the telescope]||Day||1+1||C2||working platform installed in front of the gregorian focal-station SX, Mounting RR on the SX side. Support from LBTI/Arcetri on running SOUL AO||
     
    141141=== Phase 4 (Science Verification / Early Science)===
    142142'''SHARK-NIR Location''' : LBT platform
    143 ||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (mins)'''||'''Category'''||'''LBTO Support'''||
    144 ||P4.1||[wiki:/docs/CommissioningPlan/P4.1 x]||Night||10||C5||AO support||
     143||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (hours)'''||'''Category'''||'''LBTO Support'''||
     144||P4.1||[wiki:/docs/CommissioningPlan/P4.1 Direct imaging mode testing]||Night||3+||C4 + C6||AO support||
     145||P4.2||[wiki:/docs/CommissioningPlan/P4.2 Coronagraphic imaging + field stabilization mode testing]||Night||3+||C4 + C6||AO support||
     146||P4.3||[wiki:/docs/CommissioningPlan/P4.3 Coronagraphic imaging + pupil stabilization mode testing]||Night||3+||C4 + C6||AO support||
     147||P4.4||[wiki:/docs/CommissioningPlan/P4.4 Long-slit spectrograph mode testing]||Night||3+||C4 + C6||AO support||
     148||P4.5||[wiki:/docs/CommissioningPlan/P4.5 x]||Night||1||C4 + C6||AO support||
     149||P4.6||[wiki:/docs/CommissioningPlan/P4.6 x]||Night||1||C4 + C6||AO support||
     150||P4.7||[wiki:/docs/CommissioningPlan/P4.7 x]||Night||1||C4 + C6||AO support||
     151||P4.8||[wiki:/docs/CommissioningPlan/P4.8 x]||Night||1||C4 + C6||AO support||
     152||P4.9||[wiki:/docs/CommissioningPlan/P4.9 x]||Night||1||C4 + C6||AO support||
     153
    145154
    146155Another Table with "science commissioning" to be added. More details soon.