    11== SHARK-NIR Commissioning Plan ==
    22
    3 This is an evolving page and the lists and activities will evolve in time as we gain more and more experience.
     3This document lays out the procedures and performance requirements for commissioning the SHARK-NIR instrument. Specifically, it lists the on-telescope activities needed to bring SHARK-NIR online for scientific exploitation starting from unpacking the boxes at LBT with the exception of the instrument installation at the LBT Bent Gregogian Central focal station.
    44
    5 Although it is mentioned as the commissioning activities list, it lists all the activities of SHARK-NIR from its unpacking at LBT till the Science Verification, with the exception of the instrument installation at the LBT Bent Gregogian Central focal station.
    6 
    7 The commissioning is broadly divided into 3 Phases:
     5The commissioning is broadly divided into three phases:
    86 **Phase 1**: We start from inspecting the boxes at LBT mountain bay, unpacking and installing the instrument at the mountain lab for alignment verification and functionality checks. All of these are daytime activities.
    97