Changes between Version 43 and Version 44 of docs/CommissioningPlan


Ignore:
Timestamp:
12/29/20 17:19:18 (4 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan

    v43 v44  
    1111 **Phase 3**: Phase 3 commences the nighttime commissioning, starting from sending preset to the telescope to testing individual SHARK-NIR observation modes for performance to the total SHARK-NIR performance. All the activities are nighttime. However, some daytime activities may be anticipated as well. By the end of this phase, SHARK-NIR is ready for early science observations. [Commissioning]
    1212
    13  **Phase 4**: SHARK-NIR is ready for the final phase of the commissioning - the science verification / early science observations. The final form of the SHARK-NIR software, observing blocks, data-reduction pipeline, etc. will be tested. The final performance of the SHARK-NIR will be analyzed using the data from this run. All the activities are nighttime. By the end of this phase, SHARK-NIR is ready for regular science operations (with some 'risk' of course for another year). [Science Verification]
     13 **Phase 4**: SHARK-NIR is ready for the final phase of the commissioning - the science verification / early science observations. The final form of the SHARK-NIR software, observing blocks, data-reduction pipeline, etc. will be tested for all the modes (and sub-modes) of the instrument. The final performance of the SHARK-NIR will be analyzed using the data from this run. All the activities are nighttime. By the end of this phase, SHARK-NIR is ready for regular science operations (with some 'risk' of course for another year). [Science Verification]
    1414
    1515
     
    9494||P2.0||[wiki:/docs/CommissioningPlan/P2.0 Installation of the SHARK-NIR at LBT platform]||Day||1 (preparation) + 1 (lift-off) + 1 (contigency)||C1||Crew members' support for the preparation, lift-off, and installation of SHARK-NIR, crane operator (mountain bay, LBT platform), safety officer, working platform installed infont of the gregorian focal-station SX, installation of electronics in LBTI/SHARK cabinet||
    9595||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Activating the instrument and testing instrument states & transitions]||Day||1||C2||support to verify the working of emergency button/stop||
    96 ||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Instrument operability and performance]||Day||0.5||C2||-||
     96||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Instrument operability and functioning]||Day||0.5||C2||-||
    9797||P2.3||[wiki:/docs/CommissioningPlan/P2.3 TCS communication test]||Day||0.5||C2||Authorise SHARK-NIR, connecting to ASM+LBTI AO system, able to send preset, receiving LBT telemetry (inc. the derotator trajectory) and details for the fitswriter, support from LBT SW team||
    9898||P2.4||[wiki:/docs/CommissioningPlan/P2.4 Align SHARK-NIR to the telescope]||Day||1+1||C2||working platform installed in front of the gregorian focal-station SX, Mounting RR on the SX side. Support from LBTI/Arcetri on running SOUL AO||
    9999||P2.5||[wiki:/docs/CommissioningPlan/P2.5 SOUL AO system test]||Day||0.5||C2||working platform installed in front of the gregorian focal-station SX, Mounting RR on the SX side. Support from LBTI/Arcetri on running SOUL AO||
    100 ||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA]||Day||0.5||C3||Mounting RR on the SX side. Support from LBTI/Arcetri on running SOUL AO||
     100||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA]||Day||0.5||C2 + C3||Mounting RR on the SX side. Support from LBTI/Arcetri on running SOUL AO||
    101101||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Looking for filter defects/effects/features]||Day||0.5||C2||Mounting RR on the SX side. Support from LBTI/Arcetri on running SOUL AO||
    102102||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Flexure tests]||Day||2.5||C2 + C3||Mounting RR on the SX side. Support from LBTI/Arcetri on running SOUL AO, the telescope need to move in elevation||