  • docs/CommissioningPlan

    v41 v42  
    2525
    2626== Category  ==
    27 The table below lists the categories of commissioning activities.
     27The table below lists the categories of commissioning activities (MAYBE BETTER TO CHANGE THE NOMENCLATURE. ALIGN CLOSE TO CALIBRATION PLAN).
    2828||'''Category Name'''||'''Category Number'''||
    2929||Installation, integration, verification|| C1 ||
     
    3737Each commissioning test/activity has a unified structure as follows:
    3838
    39 -----
     39{{{
     40Name of the commissioning activity
     41  - phase : states the phase of the commissioning (1/2/3/4)
     42  - status : reports the current status of the test (draft, final, complete)
     43  - category : one of the categories mentioned above
     44  - recurrence : describes how frequently the test must be executed
     45  - duration : estimates the time required to complete the test (the duration mentioned here is valid only for commissioning)
    4046
    41 === Name of the commissioning activity
    42  - {{{phase}}}: states the phase of the commissioning (1/2/3)
    43  - {{{status}}}: reports the current status of the test (draft, final, complete)
    44  - {{{category}}}: one of the categories mentioned above
    45  - {{{recurrence}}}: describes how frequently the test must be executed
    46  - {{{duration}}}: estimates the time required to complete the test
    47 === Description
    48 •       Contains a general description of the test
    49 === Prerequisites
    50 •       Lists items that must be in place before the test begins
    51 === Procedure
    52 •       Explains in detail how to execute the test
    53 === Success Criteria
    54 •       Enumerates the outcome associates with successful completion of the test
    55 === Notes
    56 •       Additional supporting information
    57 === LBTO Support
    58 •       Mention if (and what) support required from LBTO
    59 === Associated SHARK-NIR personnel
    60 •       Mentions here who are the associated personnel to the test
    61 === Date performed and by whom
    62 •       Mentions who performed the test and when
    63 -----
    64 == Additional Information  ==
     47Description
     48  - Contains a general description of the test
    6549
    66 Note:
    67  - as of now, there is no one to one correspondence with the evolving doc (eventually they will be the same)
    68  - you may see that there is some repetition in the activities. this needs to be sorted out eventually.
    69  - the order of the activities may also be changed later.
    70  - the details of each of the activity (when you click on them individually) may not be complete and will be refined in time.
     50Prerequisites
     51  - Lists items that must be in place before the test begins
    7152
    72 To be added:
    73  1. Nighttime performance activities:
    74       - Evaluate the seeing performance and Strehl achieved from the LBTI AO in closed-loop and various seeing conditions.
     53Procedure
     54  - Explains in detail how to execute the test
    7555
    76  2. Look-up table activities:
    77       -  NCPA measurement for different telescope elevations?
     56Success Criteria
     57  - Enumerates the outcome associates with successful completion of the test
    7858
     59Notes
     60  - Additional supporting information
    7961
     62LBTO Support
     63  - Mention if (and what) support required from LBTO
    8064
    81 Reminders:
    82  - The space requirements at the mountain bay (@LBT) should be communicated to LBT at the earliest, along with the availability of crane operator, container moving tools, etc. Depending upon the month of the year, the mountain bay can be seriously booked (especially during July-October months due to summer shutdown).
    83  - The same is true for the cleanroom near the mountain bay. If we need access to the LBTO network in the cleanroom, there are some network ports. But we may need to tell them in advance (Talk to Florian Briegel for more info).
    84  - Note that if there is any ASM repair/activity scheduled in the cleanroom, preference is always for them and we will have to co-live or get after that.
    85  - From the LINC-NIRVANA commissioning experience, it is always better to keep the tools associated with a particular alignment together, to avoid looking for it in all the boxes there. Also, there MUST be a **living inventory** wiki page where everyone should note down what is taken and kept in the box/container.
    86  -  Space required by SHARK-NIR at 3L is already mentioned to JC and CV. Later, we may need to specify the exact area.
    87  - For activities (P2.4-P2.8) which need the RR to be mounted on the SX side, the source should be a bright broad-band source (including also NIR wavelength). Perhaps, Ocean Optics would do. Also, if helpful, we may use a powerful (green) laser beam for initial alignment checks.
     65Associated SHARK-NIR personnel
     66  - Mentions here who are the associated personnel to the test
     67
     68Date performed and by whom
     69  - Mentions who performed the test and when
     70
     71}}}
     72
    8873
    8974== Commissioning Activity ==
     
    158143Another Table with "science commissioning" to be added. More details soon..
    159144
     145== Additional Information  ==
     146
     147Note:
     148 - as of now, there is no one to one correspondence with the evolving doc (eventually they will be the same)
     149 - you may see that there is some repetition in the activities. this needs to be sorted out eventually.
     150 - the order of the activities may also be changed later.
     151 - the details of each of the activity (when you click on them individually) may not be complete and will be refined in time.
     152
     153To be added:
     154 1. Nighttime performance activities:
     155      - Evaluate the seeing performance and Strehl achieved from the LBTI AO in closed-loop and various seeing conditions.
     156
     157 2. Look-up table activities:
     158      -  NCPA measurement for different telescope elevations?
     159
     160
     161
     162Reminders:
     163 - The space requirements at the mountain bay (@LBT) should be communicated to LBT at the earliest, along with the availability of crane operator, container moving tools, etc. Depending upon the month of the year, the mountain bay can be seriously booked (especially during July-October months due to summer shutdown).
     164 - The same is true for the cleanroom near the mountain bay. If we need access to the LBTO network in the cleanroom, there are some network ports. But we may need to tell them in advance (Talk to Florian Briegel for more info).
     165 - Note that if there is any ASM repair/activity scheduled in the cleanroom, preference is always for them and we will have to co-live or get after that.
     166 - From the LINC-NIRVANA commissioning experience, it is always better to keep the tools associated with a particular alignment together, to avoid looking for it in all the boxes there. Also, there MUST be a **living inventory** wiki page where everyone should note down what is taken and kept in the box/container.
     167 -  Space required by SHARK-NIR at 3L is already mentioned to JC and CV. Later, we may need to specify the exact area.
     168 - For activities (P2.4-P2.8) which need the RR to be mounted on the SX side, the source should be a bright broad-band source (including also NIR wavelength). Perhaps, Ocean Optics would do. Also, if helpful, we may use a powerful (green) laser beam for initial alignment checks.
     169
     170
    160171== Comments ==