Changes between Version 341 and Version 342 of docs/CommissioningPlan
- Timestamp:
- 11/16/23 17:57:08 (12 months ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan
v341 v342 313 313 || ||**Total duration with 5% contingency**||**21** nights|| 314 314 315 [[span(style=color: green, **SN-ES-Run-1 (24-29 October 2023) is complete**)]]. During the run, some commissioning activity were also performed. 316 315 [[span(style=color: green, **SN-ES-Run-1 (24-29 October 2023) is complete**)]]. During the run, some commissioning activity were also performed. The SN-ES-Run-1 activity log in this [https://docs.google.com/document/d/16rTHtiuZk6xqdvuU_pCdiPIQKaswMyGBgyjs3qfXT5k/edit link]. 317 316 318 317 - When Phase 4 science verification completes, SHARK-NIR may be offered to the community under shared-risk!!!