  • docs/CommissioningPlan

    v326 v327  
    237237||Test||Test / Correction following previous Com-Run-#||4||bad||C5|| ||
    238238||P3.3 ||[wiki:/docs/CommissioningPlan/P3.3 Pupil alignment] (for SP-1, GL and FQPM)||1||bad||C5 + C6||[[span(style=color: blue, completed for GL ans SP-1 in Com-Run-1/2  )]]||
    239 ||P3.4||[wiki:/docs/CommissioningPlan/P3.4 PSF Alignment] (for SP-1, GL and FQPM)||2||good / medium||C5 + C6||[[span(style=color: blue, completed for GL and SP1 in Com-Run-1/2  )]]||
     239||P3.4||[wiki:/docs/CommissioningPlan/P3.4 PSF Alignment] (for SP-1, GL and FQPM)||2||good / medium||C5 + C6||[[span(style=color: blue, completed for GL and SP-1 in Com-Run-1/2  )]]||
    240240||P3.14 ||[wiki:/docs/CommissioningPlan/P3.14 Star center Fourier mode images]||1||good / medium||C5 + C6||[[span(style=color: green, complete, but checks at fainter magnitudes in Com-3, low priority)]]|| ||
    241241||P3.15 ||[wiki:/docs/CommissioningPlan/P3.15 Flux calibration (off-centered target observation)]  (for GL and FQPM and SP-1 )||2||good / medium||C5 + C6||[[span(style=color: blue, partially completed in Com-Run-1/2, to be continued in Com-3  )]]||
     
    269269|| || Total duration without contingency|| 28 hours = 3.11 nights ||Assumption: 1 night = 9 hours||
    270270|| || **Total duration with 15% contingency (rounded up)**||**4** nights||
     271
     272[[span(style=color: green, **Com-Run-3 (2-6 May 2023) is complete**)]]. The Com-Run-3 activity log in this [https://docs.google.com/document/d/1lDOUuO0K9YQfYuczFeEx4WWpydjm3BGOAsUVvt5vNbA/edit# link].
     273
    271274'' Phase 4 science verification of the observing cases (8-13) may start after Com-Run-3.''