Changes between Version 309 and Version 310 of docs/CommissioningPlan


Ignore:
Timestamp:
12/02/22 12:03:04 (2 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan

    v309 v310  
    88|| 0.3 || 14-Jan-2022 || All || Minor corrections and additions || KRA ||
    99|| 0.4 || 28-Feb-2022 || First page, Phase 1 (especially P1.3, P1.4, and P1.6) || LBTO Support is removed from the table. It can be seen inside individual activities. Minor modifications following RFA-78, RFA-79, and RFA-88. || KRA ||
    10 || 0.5 || 17-Mar-2022 || P1.3 activity ||Added a picture showing the space taken by the SHARK-NIR system in cleanroom (Padova)|| KRA ||
    11 || 0.6 || 21-Apr-2022 || All ||Re-arranging the Phase1, Phase 2, and Phase 3 in terms of actual runs to LBT. Also, updating the activities according to the latest information and experience || KRA ||
     10|| 0.5 || 17-Mar-2022 || P1.3 activity ||Added a picture showing the space taken by the SHARK-NIR system in the cleanroom (Padova)|| KRA ||
     11|| 0.6 || 21-Apr-2022 || All ||Re-arranging Phase 1, Phase 2, and Phase 3 in terms of actual runs to LBT. Also, updating the activities according to the latest information and experience || KRA ||
    1212|| 0.7 || 18-May-2022 || First page Phase 1 table ||Updating the duration for the re-alignment|| KRA ||
    1313|| 0.8 || 13-Aug-2022 || First page Phase 1 & 2 tables, P1.1 to P1.12 ||Updating after Pre-Com-Run-1|| KRA ||
    1414|| 0.9 || 21-Sept-2022 || First page Phase 2 table, P2.5 to P2.10 ||Updating before Pre-Com-Run-2|| KRA ||
    1515|| 1.0 || 28-Oct-2022 || First page Phase 2 table, P1.8, P2.1 to P2.10 ||Updating before Pre-Com-Run-3|| KRA, MBE ||
    16 || 1.1 || 02-Dec-2022 || First page Phase 2 table, P1.7, P1.9, P2.1 to P2.10 ||Updating after Pre-Com-Run-3|| KRA ||
     16|| 1.1 || 02-Dec-2022 || First page Phase 2 table, P1.7, P1.9, P2.1 to P2.10, and P3.1 to P3.19 ||Updating after Pre-Com-Run-3|| KRA ||