docs/CommissioningPlan
v307 v308 184 184 || || Total without contingency||12 days || 185 185 || || Total with 10% contingency||**13 days** || 186 [[span(style=color: green, **Pre-Com-Run-3 (10-24 November 2022) iscompleted**)]]. The Pre-Com-Run-3 activity log in this [https://docs.google.com/document/d/1fYgeR-pu_lNgZE4gLrYJ3335OtDDleGAxxuGYEzEOm0/edit# link].186 [[span(style=color: green, **Pre-Com-Run-3 (10-24 November 2022) completed**)]]. The Pre-Com-Run-3 activity log in this [https://docs.google.com/document/d/1fYgeR-pu_lNgZE4gLrYJ3335OtDDleGAxxuGYEzEOm0/edit# link]. 187 187 188 188 === Phase 3 (Commissioning)===