    179179||P2.7||[wiki:/docs/CommissioningPlan/P2.7 SHARK-NIR system level NCPA characterization at different telescope elevations]||4||C3 + C4||[[span(style=color: green, complete (only for Zenith) )]]||
    180180||P2.5||[wiki:/docs/CommissioningPlan/P2.5 TCS communication test]||1||C3||[[span(style=color:blue, ongoing (remotely) )]]||
    181 ||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Verification of the mask centering algorithm and final contrast with SOUL-AO and turbulence at ASM]||3||C3||[[span(style=color: green, complete )]]||
    182 ||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Star center Fourier mode images]||1||C3||[[span(style=color: green, complete )]]||
    183 ||P2.10||[wiki:/docs/CommissioningPlan/P2.10 Test of all the remaining templates for sky observations]||2||C3||[[span(style=color: green, complete )]]||
     181||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Verification of the mask centering algorithm and final contrast with SOUL-AO and turbulence at ASM]||3||C3||[[span(style=color: green, complete (analysis pending))]]||
     182||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Star center Fourier mode images]||1||C3||[[span(style=color: blue, Scheduled (with remote support) )]]||
     183||P2.10||[wiki:/docs/CommissioningPlan/P2.10 Test of all the remaining templates for sky observations]||2||C3||[[span(style=color: green, complete (rest of the testing on-sky) )]]||
    184184|| || Total without contingency||12 days  ||
    185185|| || Total with 10% contingency||**13 days** ||