    177177||'''#'''||'''Activity Name'''||'''Duration (days)'''||'''Category'''||'''Status'''||
    178178||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Tip-Tilt internal fast loop test with ASM turbulence]||1||C3||[[span(style=color:green, complete )]]||
    179 ||P2.7||[wiki:/docs/CommissioningPlan/P2.7 SHARK-NIR system level NCPA characterization at different telescope elevations]||4||C3 + C4||[[span(style=color:blue, ongoing )]]||
    180 ||P2.5||[wiki:/docs/CommissioningPlan/P2.5 TCS communication test]||1||C3||[[span(style=color:blue, ongoing )]]||
    181 ||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Verification of the mask centering algorithm and final contrast with SOUL-AO and turbulence at ASM]||3||C3||[[span(style=color:blue, yet to start )]]||
    182 ||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Star center Fourier mode images]||1||C3||[[span(style=color:blue, yet to start )]]||
    183 ||P2.10||[wiki:/docs/CommissioningPlan/P2.10 Test of all the remaining templates for sky observations]||2||C3||[[span(style=color:blue, yet to start )]]||
     179||P2.7||[wiki:/docs/CommissioningPlan/P2.7 SHARK-NIR system level NCPA characterization at different telescope elevations]||4||C3 + C4||[[span(style=color: green, complete (only for Zenith) )]]||
     180||P2.5||[wiki:/docs/CommissioningPlan/P2.5 TCS communication test]||1||C3||[[span(style=color:blue, ongoing (remotely) )]]||
     181||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Verification of the mask centering algorithm and final contrast with SOUL-AO and turbulence at ASM]||3||C3||[[span(style=color: green, complete )]]||
     182||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Star center Fourier mode images]||1||C3||[[span(style=color: green, complete )]]||
     183||P2.10||[wiki:/docs/CommissioningPlan/P2.10 Test of all the remaining templates for sky observations]||2||C3||[[span(style=color: green, complete )]]||
    184184|| || Total without contingency||12 days  ||
    185185|| || Total with 10% contingency||**13 days** ||
    186 [[span(style=color: blue, **Pre-Com-Run-3 (10-24 November 2022) is ongoing**)]]. The Pre-Com-Run-3 activity log in this [https://docs.google.com/document/d/1fYgeR-pu_lNgZE4gLrYJ3335OtDDleGAxxuGYEzEOm0/edit# link].
     186[[span(style=color: green, **Pre-Com-Run-3 (10-24 November 2022) is completed**)]]. The Pre-Com-Run-3 activity log in this [https://docs.google.com/document/d/1fYgeR-pu_lNgZE4gLrYJ3335OtDDleGAxxuGYEzEOm0/edit# link].