Changes between Version 299 and Version 300 of docs/CommissioningPlan
- Timestamp:
- 10/28/22 18:39:32 (2 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan
v299 v300 176 176 ||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Tip-Tilt internal fast loop test with ASM turbulence]||0.5||C3|| 177 177 ||P2.7||[wiki:/docs/CommissioningPlan/P2.7 SHARK-NIR system level NCPA characterization at different telescope elevations]||4.5||C3 + C4|| 178 ||P2.5||[wiki:/docs/CommissioningPlan/P2.5 Instrument functional checks includingTCS communication test]||1||C3||178 ||P2.5||[wiki:/docs/CommissioningPlan/P2.5 TCS communication test]||1||C3|| 179 179 ||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Verification of the mask centering algorithm and final contrast with SOUL-AO and turbulence at ASM]||3||C3|| 180 180 ||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Star center Fourier mode images]||1||C3||