v2 v3 147 147 - Note that if there is any ASM repair/activity scheduled in the clean room, preference is always for them and we will have to co-live or get after that. 148 148 - From the LINC-NIRVANA commissioning experience, it is always better to keep the tools associated with a particular alignment together, to avoid looking for it in all the boxes there. Also, there MUST be a **living inventory** wiki page where everyone should note down what is taken and kept in the box/container. 149 - 149 - Space required by SHARK-NIR at 3L is already mentioned to JC and CV. Later, we may need to specify the exact area. 150 150 151 151