Changes between Version 296 and Version 297 of docs/CommissioningPlan
- Timestamp:
- 10/21/22 11:15:58 (2 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan
v296 v297 155 155 || || Total with 10% contingency||**14 days** || 156 156 157 [[span(style=color: green, **Pre-Com-Run-1 ( 12June 2022 - 12 July 2022) completed**)]]. The Pre-Com-Run-1 activity log in this [https://docs.google.com/document/d/1X1dkz5JAI9Ss7tQjugFbAjY1Jymtiy5gCBOZJ2f-s2Q/edit#heading=h.xiopfalreq1a link].157 [[span(style=color: green, **Pre-Com-Run-1 (27 June 2022 - 12 July 2022) completed**)]]. The Pre-Com-Run-1 activity log in this [https://docs.google.com/document/d/1X1dkz5JAI9Ss7tQjugFbAjY1Jymtiy5gCBOZJ2f-s2Q/edit#heading=h.xiopfalreq1a link]. 158 158 159 159 === Phase 2 (Pre-commissioning)===