    155155|| || Total with 10% contingency||**14 days** ||
    156156
    157 [[span(style=color: green, **Pre-Com-Run-1 (12 June 2022 - 12 July 2022) completed**)]]. The Pre-Com-Run-1 activity log in this [https://docs.google.com/document/d/1X1dkz5JAI9Ss7tQjugFbAjY1Jymtiy5gCBOZJ2f-s2Q/edit#heading=h.xiopfalreq1a link].
     157[[span(style=color: green, **Pre-Com-Run-1 (27 June 2022 - 12 July 2022) completed**)]]. The Pre-Com-Run-1 activity log in this [https://docs.google.com/document/d/1X1dkz5JAI9Ss7tQjugFbAjY1Jymtiy5gCBOZJ2f-s2Q/edit#heading=h.xiopfalreq1a link].
    158158