    166166||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Installation of SHARK-NIR and its electronics on the LBT platform]||7||C2||[[span(style=color:green, complete )]]||
    167167||P2.3||[wiki:/docs/CommissioningPlan/P2.3 Basic functionality,  Instrument operability and functioning]||1||C3||[[span(style=color:green, complete )]]||
    168 ||P2.4||[wiki:/docs/CommissioningPlan/P2.4 SHARK-NIR alignment to the telescope]||3||C3||[[span(style=color:blue, on-going)]]||
     168||P2.4||[wiki:/docs/CommissioningPlan/P2.4 SHARK-NIR alignment to the telescope]||3||C3||[[span(style=color:green, complete )]]||
    169169|| || Total without contingency||14 days  ||
    170170|| || Total with 10% contingency||**15.5 days** ||
    171171
    172 The Pre-Com-Run-2 activity log in this [https://docs.google.com/document/d/1g18DLn96Rxgy2KUpWZb3D4WhlxAZvkj0miG0dK8wr6s/edit#heading=h.xiopfalreq1a link].
     172[[span(style=color: green, **Pre-Com-Run-2 (3-19 October 202) completed**)]]. The Pre-Com-Run-2 activity log in this [https://docs.google.com/document/d/1g18DLn96Rxgy2KUpWZb3D4WhlxAZvkj0miG0dK8wr6s/edit#heading=h.xiopfalreq1a link].
    173173
    174174**__Pre-Com-Run-3__**