    164164||P2.0||[wiki:/docs/CommissioningPlan/P2.0 SHARK-NIR Open Cart Activities]||1||C1||[[span(style=color:green, complete )]]||
    165165||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Cable chain cabling and pre-lift verification]||2||C1||[[span(style=color:green, complete)]]||
    166 ||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Installation of SHARK-NIR and its electronics on the LBT platform]||7||C2||[[span(style=color:blue, on-going)]]||
    167 ||P2.3||[wiki:/docs/CommissioningPlan/P2.3 Basic functionality,  Instrument operability and functioning]||1||C3||[[span(style=color:blue, yet to start)]]||
    168 ||P2.4||[wiki:/docs/CommissioningPlan/P2.4 SHARK-NIR alignment to the telescope]||3||C3||[[span(style=color:blue, yet to start)]]||
     166||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Installation of SHARK-NIR and its electronics on the LBT platform]||7||C2||[[span(style=color:green, complete )]]||
     167||P2.3||[wiki:/docs/CommissioningPlan/P2.3 Basic functionality,  Instrument operability and functioning]||1||C3||[[span(style=color:green, complete )]]||
     168||P2.4||[wiki:/docs/CommissioningPlan/P2.4 SHARK-NIR alignment to the telescope]||3||C3||[[span(style=color:blue, on-going)]]||
    169169|| || Total without contingency||14 days  ||
    170170|| || Total with 10% contingency||**15.5 days** ||