164 | | ||P2.0||[wiki:/docs/CommissioningPlan/P2.0 SHARK-NIR Open Cart Activities]||1||C1||[[span(style=color:blue, on-going )]]|| |
165 | | ||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Cable chain cabling and pre-lift verification]||2||C1||[[span(style=color:blue, on-going )]]|| |
166 | | ||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Installation of SHARK-NIR and its electronics on the LBT platform]||7||C2||[[span(style=color:blue, yet to start)]]|| |
| 164 | ||P2.0||[wiki:/docs/CommissioningPlan/P2.0 SHARK-NIR Open Cart Activities]||1||C1||[[span(style=color:green, complete )]]|| |
| 165 | ||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Cable chain cabling and pre-lift verification]||2||C1||[[span(style=color:green, complete)]]|| |
| 166 | ||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Installation of SHARK-NIR and its electronics on the LBT platform]||7||C2||[[span(style=color:blue, on-going)]]|| |