163 | | ||'''#'''||'''Activity Name'''||'''Duration (days)'''||'''Category'''|| |
164 | | ||P2.0||[wiki:/docs/CommissioningPlan/P2.0 SHARK-NIR Open Cart Activities]||1||C1|| |
165 | | ||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Cable chain cabling and pre-lift verification]||2||C1|| |
166 | | ||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Installation of SHARK-NIR and its electronics on the LBT platform]||7||C2|| |
167 | | ||P2.3||[wiki:/docs/CommissioningPlan/P2.3 Basic functionality, Instrument operability and functioning]||1||C3|| |
168 | | ||P2.4||[wiki:/docs/CommissioningPlan/P2.4 SHARK-NIR alignment to the telescope]||3||C3|| |
| 163 | ||'''#'''||'''Activity Name'''||'''Duration (days)'''||'''Category'''||'''Status'''|| |
| 164 | ||P2.0||[wiki:/docs/CommissioningPlan/P2.0 SHARK-NIR Open Cart Activities]||1||C1||[[span(style=color:blue, on-going )]]|| |
| 165 | ||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Cable chain cabling and pre-lift verification]||2||C1||[[span(style=color:blue, on-going )]]|| |
| 166 | ||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Installation of SHARK-NIR and its electronics on the LBT platform]||7||C2||[[span(style=color:blue, yet to start)]]|| |
| 167 | ||P2.3||[wiki:/docs/CommissioningPlan/P2.3 Basic functionality, Instrument operability and functioning]||1||C3||[[span(style=color:blue, yet to start)]]|| |
| 168 | ||P2.4||[wiki:/docs/CommissioningPlan/P2.4 SHARK-NIR alignment to the telescope]||3||C3||[[span(style=color:blue, yet to start)]]|| |