    180180|| || Total with 10% contingency||**12.5 days** ||
    181181
     182**__Pre-Com-Run-3__Luca&Jacopo_work_in_progress**
     183||'''#'''||'''Activity Name'''||'''Duration (days)'''||'''Category'''||
     184||P2.5||[wiki:/docs/CommissioningPlan/P2.5 Instrument functional checks including TCS communication test]||1||C3||
     185||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Tip-Tilt internal fast loop test with ASM turbulence]||0.5||C3 + C4||
     186||P2.7||[wiki:/docs/CommissioningPlan/P2.7 SHARK-NIR NCPA characterization at different telescope elevations]||4||C3 + C4||
     187||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Star center Fourier mode images]||1||C3||
     188||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Verification of the mask centering algorithm and final contrast with SOUL-AO and turbulence at ASM]||3||C3 + C4||
     189||P2.10||[wiki:/docs/CommissioningPlan/P2.10 Test of all the remaining templates for sky observations TBD]||TBD||C3 + C4||
     190|| || Total without contingency||9.5 days  ||
     191|| || Total with 10% contingency||**10.5 days**||
     192
    182193=== Phase 3 (Commissioning)===
    183194'''SHARK-NIR Location''': LBT platform. All activities are __nightime__. Some daytime (within SHARK-NIR) may be required. Also, the SHARK-NIR software, SHINS, is expected to be almost ready to be tested.