Changes between Version 286 and Version 287 of docs/CommissioningPlan


Ignore:
Timestamp:
08/26/22 12:15:10 (2 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan

    v286 v287  
    165165||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Cable chain cabling and pre-lift verification]||2||C1||
    166166||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Installation of SHARK-NIR and its electronics on the LBT platform]||7||C2||
    167 ||P2.3||[wiki:/docs/CommissioningPlan/P2.1 Basic functionality,  Instrument operability and functioning]||1||C3||
     167||P2.3||[wiki:/docs/CommissioningPlan/P2.3 Basic functionality,  Instrument operability and functioning]||1||C3||
    168168||P2.4||[wiki:/docs/CommissioningPlan/P2.4 SHARK-NIR alignment to the telescope]||3||C3||
    169169|| || Total without contingency||14 days  ||
     
    172172**__Pre-Com-Run-3__**
    173173||'''#'''||'''Activity Name'''||'''Duration (days)'''||'''Category'''||
    174 ||P2.3||[wiki:/docs/CommissioningPlan/P2.3 TCS communication test]||1||C3||
    175 ||P2.5||[wiki:/docs/CommissioningPlan/P2.5 Cryostat Cooldown and Science detector calibrations]||1||C3 + C4||
    176 ||P2.6||[wiki:/docs/CommissioningPlan/P2.6 SHARK-NIR system level characterization at different telescope elevations]||6||C3 + C4||
    177 ||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Star center Fourier mode images]||0.5||C3||
    178 ||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Verification of the mask centering algorithm and final contrast with SOUL-AO and turbulence at ASM]||3||C3 + C4||
     174||P2.5||[wiki:/docs/CommissioningPlan/P2.5 TCS communication test]||1||C3||
     175||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Cryostat Cooldown and Science detector calibrations]||1||C3 + C4||
     176||P2.7||[wiki:/docs/CommissioningPlan/P2.7 SHARK-NIR system level characterization at different telescope elevations]||6||C3 + C4||
     177||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Star center Fourier mode images]||0.5||C3||
     178||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Verification of the mask centering algorithm and final contrast with SOUL-AO and turbulence at ASM]||3||C3 + C4||
    179179|| || Total without contingency||11.5 days  ||
    180180|| || Total with 10% contingency||**12.5 days** ||