Changes between Version 283 and Version 284 of docs/CommissioningPlan
- Timestamp:
- 08/26/22 11:01:29 (2 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan
v283 v284 162 162 **__Pre-Com-Run-2__** 163 163 ||'''#'''||'''Activity Name'''||'''Duration (days)'''||'''Category'''|| 164 ||P2.0||[wiki:/docs/CommissioningPlan/P2.0 _SHARK-NIR Open Cart Activities]||1||C1||164 ||P2.0||[wiki:/docs/CommissioningPlan/P2.0 SHARK-NIR Open Cart Activities]||1||C1|| 165 165 ||P2.0_Pre||[wiki:/docs/CommissioningPlan/P2.0_Pre Cable chain cabling and pre-lift verification]||2||C1|| 166 166 ||P2.0A||[wiki:/docs/CommissioningPlan/P2.0A Installation of SHARK-NIR and electronics on the LBT platform]||7||C2||