docs/CommissioningPlan
v282 v283 162 162 **__Pre-Com-Run-2__** 163 163 ||'''#'''||'''Activity Name'''||'''Duration (days)'''||'''Category'''|| 164 ||P2.0 _Pre||[wiki:/docs/CommissioningPlan/P2.0_Pre Oil the rotatory stages on the SHARK-NIR]||1||C1||164 ||P2.0||[wiki:/docs/CommissioningPlan/P2.0_SHARK-NIR Open Cart Activities]||1||C1|| 165 165 ||P2.0_Pre||[wiki:/docs/CommissioningPlan/P2.0_Pre Cable chain cabling and pre-lift verification]||2||C1|| 166 166 ||P2.0A||[wiki:/docs/CommissioningPlan/P2.0A Installation of SHARK-NIR and electronics on the LBT platform]||7||C2||