    162162**__Pre-Com-Run-2__**
    163163||'''#'''||'''Activity Name'''||'''Duration (days)'''||'''Category'''||
    164 ||P2.0_Pre||[wiki:/docs/CommissioningPlan/P2.0_Pre Oil the rotatory stages on the SHARK-NIR]||1||C1||
     164||P2.0||[wiki:/docs/CommissioningPlan/P2.0_SHARK-NIR Open Cart Activities]||1||C1||
    165165||P2.0_Pre||[wiki:/docs/CommissioningPlan/P2.0_Pre Cable chain cabling and pre-lift verification]||2||C1||
    166166||P2.0A||[wiki:/docs/CommissioningPlan/P2.0A Installation of SHARK-NIR and electronics on the LBT platform]||7||C2||