    272272Every evening of the nighttime commissioning, all the required calibrations (including dark, bias, flat-field, etc. for all the filters required) will be taken using the SHARK-NIR calibration unit.
    273273
    274 **__SV-Run-1__**
     274**__SN-SV-Run-1__**
    275275||'''#'''||'''Activity Name / Observing Case'''||'''Duration (nights)'''||'''Seeing Conditions'''||'''Category'''||
    276276||P4.1||[wiki:/docs/CommissioningPlan/P4.1 Exo-planet: Giant planets and brown dwarfs in SFR, stellar associations, & young open clusters]||8|| ||C8||