Changes between Version 278 and Version 279 of docs/CommissioningPlan


Ignore:
Timestamp:
08/13/22 08:24:55 (2 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan

    v278 v279  
    1111|| 0.6 || 21-Apr-2022 || All ||Re-arranging the Phase1, Phase 2, and Phase 3 in terms of actual runs to LBT. Also, updating the activities according to the latest information and experience || KRA ||
    1212|| 0.7 || 18-May-2022 || First page Phase 1 table ||Updating the duration for the re-alignment|| KRA ||
    13 || 0.8 || 13-Aug-2022 || First page Phase 1 tables, P1.1 to P1.12 ||Updating after Pre-Com-Run-1|| KRA ||
     13|| 0.8 || 13-Aug-2022 || First page Phase 1 & 2 tables, P1.1 to P1.12 ||Updating after Pre-Com-Run-1|| KRA ||
    1414
    1515