docs/CommissioningPlan
v276 v277 162 162 **__Pre-Com-Run-2__** 163 163 ||'''#'''||'''Activity Name'''||'''Duration (days)'''||'''Category'''|| 164 ||P2.0 -Pre||[wiki:/docs/CommissioningPlan/P2.0-Pre Cable chain cabling and pre-lift verification]||2||C1||164 ||P2.0_Pre||[wiki:/docs/CommissioningPlan/P2.0_Pre Cable chain cabling and pre-lift verification]||2||C1|| 165 165 ||P2.0A||[wiki:/docs/CommissioningPlan/P2.0A Installation of SHARK-NIR on LBT platform]||6||C2|| 166 166 ||P2.0B||[wiki:/docs/CommissioningPlan/P2.0B Installation of SHARK-NIR electronics on LBT platform]||2||C2||