Changes between Version 269 and Version 270 of docs/CommissioningPlan


Ignore:
Timestamp:
05/18/22 14:49:17 (2 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan

    v269 v270  
    1 = SHARK-NIR Commissioning Plan (SHARK-NIR-INAFP-COM-001 Issue 0.6)=
     1= SHARK-NIR Commissioning Plan (SHARK-NIR-INAFP-COM-001 Issue 0.7)=
    22[[TOC(inline)]]
    33
     
    99|| 0.4 || 28-Feb-2022 || First page, Phase 1 (especially P1.3, P1.4, and P1.6) || LBTO Support is removed from the table. It can be seen inside individual activities. Minor modifications in accordance with  RFA-78, RFA-79, RFA-88. || KRA ||
    1010|| 0.5 || 17-Mar-2022 || P1.3 activity ||Added a picture showing the space taken by the SHARK-NIR system in cleanroom (Padova)|| KRA ||
    11 || 0.6 || 21-Apr-2022 || All ||Re-arranging the Phase1, Phase 2, and Phase 3 in terms of actual runs to LBT. Also updating the activities according to latest information and experience|| KRA ||
     11|| 0.6 || 21-Apr-2022 || All ||Re-arranging the Phase1, Phase 2, and Phase 3 in terms of actual runs to LBT. Also updating the activities according to latest
     12|| 0.7 || 18-May-2022 || First page Phase 1 table ||Updating the duration for the re-alignment|| KRA ||
    1213
    1314== Applicable Documents ==
     
    2930This commissioning planning document lays out and details the activities needed to bring SHARK-NIR online for __single-eye shared-risk scientific exploitation__ (the binocular observations with SHARK-VIS or trinocular with SHARK-VIS & LBTI are out of the scope of this commissioning plan). The document incorporates activities starting from the unpacking of the boxes at the LBT mountain bay to the science verification at its final destination on the LBT platform. Although called the commissioning document, it lists the pre-commissioning, commissioning, and science verification activities. The activities are classified into four phases.  Phases 1 and 2 are purely daytime activities. Phases 3 and 4 are nighttime activities. It is to be noted that Phase 3 activities are classified into observing cases (OC#, see the table below) and '''not''' according to the observing modes (direct imaging, coronagraphic imaging, long-slit spectroscopy) anymore. This allows commencing Phase 4 (science verification) of those observing cases immediately after the completion of the respective Phase 3 commissioning run. See below for more details.
    3031
    31  **Phase 1**: We start by inspecting the boxes at LBT mountain bay, unpacking, and installing the instrument at the mountain lab (clean room) for alignment verification and functionality checks. All of these are daytime activities (1 trip to LBT). This forms the content of the __PSR-09 Preliminary Laboratory Integration & Test (I&T) Procedure__ (at LBT). [Pre-commissioning: Unpack, assemble, and clean-room verification]
     32 **Phase 1**: We start by inspecting the boxes at LBT mountain bay, unpacking, and installing the instrument at the mountain lab (clean room) for alignment verification and functionality checks. All of these are daytime activities. We anticipate 1 trip to LBT if no or minor re-alignment is required. If a major re-alignment is required, there will be 2 trips to LBT. This forms the content of the __PSR-09 Preliminary Laboratory Integration & Test (I&T) Procedure__ (at LBT). [Pre-commissioning: Unpack, assemble, and clean-room verification]
    3233
    3334 **Phase 2**: The activities start from the installation of SHARK-NIR at the SX central bent Gregorian focus of LBT, followed by preliminary functional checks, aligning SHARK-NIR to the telescope (daytime), and daytime closed dome engineering/technical testing. All of these are daytime activities (2 trips to LBT). [Pre-commissioning: Installation, functional checks, and closed-dome testing]
     
    138139||P1.9||[wiki:/docs/CommissioningPlan/P1.9 Testing of SCICAM image grabbing by SOUL-AO]||0.5||C3||
    139140||P1.10||[wiki:/docs/CommissioningPlan/P1.10 Internal alignment verification]||1||C1||
    140 ||P1.11||[wiki:/docs/CommissioningPlan/P1.11 Instrument re-alignment]||1 - 6||C1||
     141||P1.11||[wiki:/docs/CommissioningPlan/P1.11 Instrument re-alignment (minor modifications)]||1||C1||
    141142||P1.12||[wiki:/docs/CommissioningPlan/P1.12 Verification of the contrast for coronagraphic masks]||1||C1||
    142 || || Total without contingency (if re-alignment is __not__ required)||11 days  ||
    143 || || Total with 10% contingency (if re-alignment is __not__ required)||**12 days** ||
    144 || || Total without contingency (if re-alignment is required)||12-17 days ||
    145 || || Total with 10% contingency (if re-alignment is required)||**13-18.5 days** ||
     143|| || Total without contingency||12 days  ||
     144|| || Total with 10% contingency (rounded up)||**14 days** ||
     145
     146**__Pre-Com-Run-1-bis__**
     147||'''#'''||'''Activity Name'''||'''Duration (days)'''||'''Category'''||
     148||P1.11||[wiki:/docs/CommissioningPlan/P1.11 Instrument re-alignment (major modifications)]||12||C1||
     149||P1.12||[wiki:/docs/CommissioningPlan/P1.12 Verification of the contrast for coronagraphic masks]||1||C1||
     150|| || Total without contingency||13 days ||
     151|| || Total with 10% contingency||**14 days** ||
    146152
    147153