129 | | ||'''#'''||'''Activity Name'''||'''Duration (days)'''||'''Category'''||'''Note'''|| |
130 | | ||P1.1||[wiki:/docs/CommissioningPlan/P1.1 Inspection of the closed boxes]||0.5||C1|| || |
131 | | ||P1.2||[wiki:/docs/CommissioningPlan/P1.2 Opening of boxes in LBT Hall, inspection of the contents and installation of units on their handlings]||1||C1|| || |
132 | | ||P1.3||[wiki:/docs/CommissioningPlan/P1.3 Installation of SHARK-NIR HW and electronics in clean room]||1.5||C1|| || |
133 | | ||P1.4||[wiki:/docs/CommissioningPlan/P1.4 Cable in the instrument, power on, install workstations, connect to LBT network, and cryostat cooldown preparation]||1||C1|| || |
134 | | ||P1.5||[wiki:/docs/CommissioningPlan/P1.5 SW & HW functional checks and cryostat cooldown]||1||C1|| || |
135 | | ||P1.6||[wiki:/docs/CommissioningPlan/P1.6 SCICAM refocussing]||1.5||C1|| || |
136 | | ||P1.7||[wiki:/docs/CommissioningPlan/P1.7 Science detector calibrations]||0.5||C3 + C4||P1.5 should be completed.|| |
137 | | ||P1.8||[wiki:/docs/CommissioningPlan/P1.8 Complete system functional verification, filter artifacts/defects verification, NCPA measurement, and internal tip-tilt loop verification]||1.5||C1||P1.7 should be completed.|| |
138 | | ||P1.9||[wiki:/docs/CommissioningPlan/P1.9 Testing of SCICAM image grabbing by SOUL-AO]||0.5||C3|| || |
139 | | ||P1.10||[wiki:/docs/CommissioningPlan/P1.10 Internal alignment verification]||1||C1|| || |
140 | | ||P1.11||[wiki:/docs/CommissioningPlan/P1.11 Instrument re-alignment]||1 - 6||C1||The duration of this activity, if needed, can be between 1 day to a maximum of 6 days.|| |
141 | | ||P1.12||[wiki:/docs/CommissioningPlan/P1.12 Verification of the contrast for coronagraphic masks]||1||C1||P1.10 (and if needed P1.11) should be completed. || |
| 129 | ||'''#'''||'''Activity Name'''||'''Duration (days)'''||'''Category'''|| |
| 130 | ||P1.1||[wiki:/docs/CommissioningPlan/P1.1 Inspection of the closed boxes]||0.5||C1|| |
| 131 | ||P1.2||[wiki:/docs/CommissioningPlan/P1.2 Opening of boxes in LBT Hall, inspection of the contents and installation of units on their handlings]||1||C1|| |
| 132 | ||P1.3||[wiki:/docs/CommissioningPlan/P1.3 Installation of SHARK-NIR HW and electronics in clean room]||1.5||C1|| |
| 133 | ||P1.4||[wiki:/docs/CommissioningPlan/P1.4 Cable in the instrument, power on, install workstations, connect to LBT network, and cryostat cooldown preparation]||1||C1|| |
| 134 | ||P1.5||[wiki:/docs/CommissioningPlan/P1.5 SW & HW functional checks and cryostat cooldown]||1||C1|| |
| 135 | ||P1.6||[wiki:/docs/CommissioningPlan/P1.6 SCICAM refocussing]||1.5||C1|| |
| 136 | ||P1.7||[wiki:/docs/CommissioningPlan/P1.7 Science detector calibrations]||0.5||C3 + C4|| |
| 137 | ||P1.8||[wiki:/docs/CommissioningPlan/P1.8 Complete system functional verification, filter artifacts/defects verification, NCPA measurement, and internal tip-tilt loop verification]||1.5||C1|| |
| 138 | ||P1.9||[wiki:/docs/CommissioningPlan/P1.9 Testing of SCICAM image grabbing by SOUL-AO]||0.5||C3|| |
| 139 | ||P1.10||[wiki:/docs/CommissioningPlan/P1.10 Internal alignment verification]||1||C1|| |
| 140 | ||P1.11||[wiki:/docs/CommissioningPlan/P1.11 Instrument re-alignment]||1 - 6||C1|| |
| 141 | ||P1.12||[wiki:/docs/CommissioningPlan/P1.12 Verification of the contrast for coronagraphic masks]||1||C1|| |
152 | | ||'''#'''||'''Activity Name'''||'''Duration (days)'''||'''Category'''||'''Note'''|| |
153 | | ||P2.0A||[wiki:/docs/CommissioningPlan/P2.0A Installation of SHARK-NIR on LBT platform]||6||C2|| || |
154 | | ||P2.0B||[wiki:/docs/CommissioningPlan/P2.0B Installation of SHARK-NIR electronics on LBT platform]||2||C2|| || |
155 | | ||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Basic functionality and shutdown procedure test, cryostat cooldown]||1||C3|| || |
156 | | ||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Instrument operability and functioning]||1||C3|| || |
157 | | ||P2.3||[wiki:/docs/CommissioningPlan/P2.3 TCS communication test]||1||C3||Although 2 days of work is required, a lot can go in parallel with other ones. For the estimation of total days, we consider 1 day. || |
158 | | ||P2.4||[wiki:/docs/CommissioningPlan/P2.4 SHARK-NIR alignment to the telescope]||3||C3|| || |
| 152 | ||'''#'''||'''Activity Name'''||'''Duration (days)'''||'''Category'''|| |
| 153 | ||P2.0A||[wiki:/docs/CommissioningPlan/P2.0A Installation of SHARK-NIR on LBT platform]||6||C2|| |
| 154 | ||P2.0B||[wiki:/docs/CommissioningPlan/P2.0B Installation of SHARK-NIR electronics on LBT platform]||2||C2|| |
| 155 | ||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Basic functionality and shutdown procedure test, cryostat cooldown]||1||C3|| |
| 156 | ||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Instrument operability and functioning]||1||C3|| |
| 157 | ||P2.3||[wiki:/docs/CommissioningPlan/P2.3 TCS communication test]||1||C3|| |
| 158 | ||P2.4||[wiki:/docs/CommissioningPlan/P2.4 SHARK-NIR alignment to the telescope]||3||C3|| |
163 | | ||'''#'''||'''Activity Name'''||'''Duration (days)'''||'''Category'''||'''Note'''|| |
164 | | ||P2.5||[wiki:/docs/CommissioningPlan/P2.5 Cryostat Cooldown and Science detector calibrations]||1||C3 + C4|| || |
165 | | ||P2.6||[wiki:/docs/CommissioningPlan/P2.6 SHARK-NIR system level characterization at different telescope elevations]||6||C3 + C4||Checking pointing offset between SHARK-NIR, LBTI, and SOUL-AO, SOUL-AO tests, and NCPA measurements.|| |
166 | | ||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Star center Fourier mode images]||0.5||C3|| || |
167 | | ||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Verification of the mask centering algorithm and final contrast with SOUL-AO and turbulence at ASM]||3||C3 + C4|| || |
| 163 | ||'''#'''||'''Activity Name'''||'''Duration (days)'''||'''Category'''|| |
| 164 | ||P2.5||[wiki:/docs/CommissioningPlan/P2.5 Cryostat Cooldown and Science detector calibrations]||1||C3 + C4|| |
| 165 | ||P2.6||[wiki:/docs/CommissioningPlan/P2.6 SHARK-NIR system level characterization at different telescope elevations]||6||C3 + C4|| |
| 166 | ||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Star center Fourier mode images]||0.5||C3|| |
| 167 | ||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Verification of the mask centering algorithm and final contrast with SOUL-AO and turbulence at ASM]||3||C3 + C4|| |