    128128**__Pre-Com-Run-1__**
    129 ||'''#'''||'''Activity Name'''||'''Duration (days)'''||'''Category'''||'''Note'''||                    
    130 ||P1.1||[wiki:/docs/CommissioningPlan/P1.1 Inspection of the closed boxes]||0.5||C1|| ||
    131 ||P1.2||[wiki:/docs/CommissioningPlan/P1.2 Opening of boxes in LBT Hall, inspection of the contents and installation of units on their handlings]||1||C1|| ||
    132 ||P1.3||[wiki:/docs/CommissioningPlan/P1.3 Installation of SHARK-NIR HW and electronics in clean room]||1.5||C1|| ||
    133 ||P1.4||[wiki:/docs/CommissioningPlan/P1.4 Cable in the instrument, power on, install workstations, connect to LBT network, and cryostat cooldown preparation]||1||C1|| ||
    134 ||P1.5||[wiki:/docs/CommissioningPlan/P1.5 SW & HW functional checks and cryostat cooldown]||1||C1|| ||
    135 ||P1.6||[wiki:/docs/CommissioningPlan/P1.6 SCICAM refocussing]||1.5||C1|| ||
    136 ||P1.7||[wiki:/docs/CommissioningPlan/P1.7 Science detector calibrations]||0.5||C3 + C4||P1.5 should be completed.||
    137 ||P1.8||[wiki:/docs/CommissioningPlan/P1.8 Complete system functional verification, filter artifacts/defects verification, NCPA measurement, and internal tip-tilt loop verification]||1.5||C1||P1.7 should be completed.||
    138 ||P1.9||[wiki:/docs/CommissioningPlan/P1.9 Testing of SCICAM image grabbing by SOUL-AO]||0.5||C3|| ||
    139 ||P1.10||[wiki:/docs/CommissioningPlan/P1.10 Internal alignment verification]||1||C1|| ||
    140 ||P1.11||[wiki:/docs/CommissioningPlan/P1.11 Instrument re-alignment]||1 - 6||C1||The duration of this activity, if needed, can be between 1 day to a maximum of 6 days.||
    141 ||P1.12||[wiki:/docs/CommissioningPlan/P1.12 Verification of the contrast for coronagraphic masks]||1||C1||P1.10 (and if needed P1.11) should be completed. ||
     129||'''#'''||'''Activity Name'''||'''Duration (days)'''||'''Category'''||
     130||P1.1||[wiki:/docs/CommissioningPlan/P1.1 Inspection of the closed boxes]||0.5||C1||
     131||P1.2||[wiki:/docs/CommissioningPlan/P1.2 Opening of boxes in LBT Hall, inspection of the contents and installation of units on their handlings]||1||C1||
     132||P1.3||[wiki:/docs/CommissioningPlan/P1.3 Installation of SHARK-NIR HW and electronics in clean room]||1.5||C1||
     133||P1.4||[wiki:/docs/CommissioningPlan/P1.4 Cable in the instrument, power on, install workstations, connect to LBT network, and cryostat cooldown preparation]||1||C1||
     134||P1.5||[wiki:/docs/CommissioningPlan/P1.5 SW & HW functional checks and cryostat cooldown]||1||C1||
     135||P1.6||[wiki:/docs/CommissioningPlan/P1.6 SCICAM refocussing]||1.5||C1||
     136||P1.7||[wiki:/docs/CommissioningPlan/P1.7 Science detector calibrations]||0.5||C3 + C4||
     137||P1.8||[wiki:/docs/CommissioningPlan/P1.8 Complete system functional verification, filter artifacts/defects verification, NCPA measurement, and internal tip-tilt loop verification]||1.5||C1||
     138||P1.9||[wiki:/docs/CommissioningPlan/P1.9 Testing of SCICAM image grabbing by SOUL-AO]||0.5||C3||
     139||P1.10||[wiki:/docs/CommissioningPlan/P1.10 Internal alignment verification]||1||C1||
     140||P1.11||[wiki:/docs/CommissioningPlan/P1.11 Instrument re-alignment]||1 - 6||C1||
     141||P1.12||[wiki:/docs/CommissioningPlan/P1.12 Verification of the contrast for coronagraphic masks]||1||C1||
    142142|| || Total without contingency (if re-alignment is __not__ required)||11 days  ||
    143143|| || Total with 10% contingency (if re-alignment is __not__ required)||**12 days** ||
     
    150150
    151151**__Pre-Com-Run-2__**
    152 ||'''#'''||'''Activity Name'''||'''Duration (days)'''||'''Category'''||'''Note'''||     
    153 ||P2.0A||[wiki:/docs/CommissioningPlan/P2.0A Installation of SHARK-NIR on LBT platform]||6||C2|| ||
    154 ||P2.0B||[wiki:/docs/CommissioningPlan/P2.0B Installation of SHARK-NIR electronics on LBT platform]||2||C2|| ||
    155 ||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Basic functionality and shutdown procedure test, cryostat cooldown]||1||C3|| ||
    156 ||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Instrument operability and functioning]||1||C3|| ||
    157 ||P2.3||[wiki:/docs/CommissioningPlan/P2.3 TCS communication test]||1||C3||Although 2 days of work is required, a lot can go in parallel with other ones. For the estimation of total days, we consider 1 day. ||
    158 ||P2.4||[wiki:/docs/CommissioningPlan/P2.4 SHARK-NIR alignment to the telescope]||3||C3|| ||
     152||'''#'''||'''Activity Name'''||'''Duration (days)'''||'''Category'''||
     153||P2.0A||[wiki:/docs/CommissioningPlan/P2.0A Installation of SHARK-NIR on LBT platform]||6||C2||
     154||P2.0B||[wiki:/docs/CommissioningPlan/P2.0B Installation of SHARK-NIR electronics on LBT platform]||2||C2||
     155||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Basic functionality and shutdown procedure test, cryostat cooldown]||1||C3||
     156||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Instrument operability and functioning]||1||C3||
     157||P2.3||[wiki:/docs/CommissioningPlan/P2.3 TCS communication test]||1||C3||
     158||P2.4||[wiki:/docs/CommissioningPlan/P2.4 SHARK-NIR alignment to the telescope]||3||C3||
    159159|| || Total without contingency||14 days  ||
    160160|| || Total with 10% contingency||**15.5 days** ||
    161161
    162162**__Pre-Com-Run-3__**
    163 ||'''#'''||'''Activity Name'''||'''Duration (days)'''||'''Category'''||'''Note'''||     
    164 ||P2.5||[wiki:/docs/CommissioningPlan/P2.5 Cryostat Cooldown and Science detector calibrations]||1||C3 + C4|| ||
    165 ||P2.6||[wiki:/docs/CommissioningPlan/P2.6 SHARK-NIR system level characterization at different telescope elevations]||6||C3 + C4||Checking pointing offset between SHARK-NIR, LBTI, and SOUL-AO, SOUL-AO tests, and NCPA measurements.||
    166 ||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Star center Fourier mode images]||0.5||C3|| ||
    167 ||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Verification of the mask centering algorithm and final contrast with SOUL-AO and turbulence at ASM]||3||C3 + C4|| ||
     163||'''#'''||'''Activity Name'''||'''Duration (days)'''||'''Category'''||
     164||P2.5||[wiki:/docs/CommissioningPlan/P2.5 Cryostat Cooldown and Science detector calibrations]||1||C3 + C4||
     165||P2.6||[wiki:/docs/CommissioningPlan/P2.6 SHARK-NIR system level characterization at different telescope elevations]||6||C3 + C4||
     166||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Star center Fourier mode images]||0.5||C3||
     167||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Verification of the mask centering algorithm and final contrast with SOUL-AO and turbulence at ASM]||3||C3 + C4||
    168168|| || Total without contingency||10.5 days  ||
    169169|| || Total with 10% contingency||**11.5 days** ||