Changes between Version 260 and Version 261 of docs/CommissioningPlan
- Timestamp:
- 04/22/22 19:15:25 (3 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan
v260 v261 157 157 ||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Basic functionality and shutdown procedure test, cryostat cooldown]||1||C3|| || 158 158 ||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Instrument operability and functioning]||1||C3|| || 159 ||P2.3||[wiki:/docs/CommissioningPlan/P2.3 TCS communication test]|| 2||C3||Although 2 days of work is required, a lot cango in parallel with other ones. For the estimation of total days, we consider 1 day. ||159 ||P2.3||[wiki:/docs/CommissioningPlan/P2.3 TCS communication test]||1||C3||Although 2 days of work is required, a lot can go in parallel with other ones. For the estimation of total days, we consider 1 day. || 160 160 ||P2.4||[wiki:/docs/CommissioningPlan/P2.4 SHARK-NIR alignment to the telescope]||3||C3|| || 161 161 || || Total without contingency||14 days ||