Changes between Version 259 and Version 260 of docs/CommissioningPlan
- Timestamp:
- 04/22/22 18:22:49 (3 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan
v259 v260 137 137 ||P1.6||[wiki:/docs/CommissioningPlan/P1.6 SCICAM refocussing]||1.5||C1|| || 138 138 ||P1.7||[wiki:/docs/CommissioningPlan/P1.7 Science detector calibrations]||0.5||C3 + C4||P1.5 should be completed.|| 139 ||P1.8||[wiki:/docs/CommissioningPlan/P1.8 Motor/light sources functional verification, filter artifacts/defects verification, and NCPA &internal tip-tilt loop verification]||1.5||C1||P1.7 should be completed.||139 ||P1.8||[wiki:/docs/CommissioningPlan/P1.8 Complete system functional verification, filter artifacts/defects verification, NCPA measurement, and internal tip-tilt loop verification]||1.5||C1||P1.7 should be completed.|| 140 140 ||P1.9||[wiki:/docs/CommissioningPlan/P1.9 Testing of SCICAM image grabbing by SOUL-AO]||0.5||C3|| || 141 141 ||P1.10||[wiki:/docs/CommissioningPlan/P1.10 Internal alignment verification]||1||C1|| ||