159 | | === Software Related Stuff / Activities / Reminders |
160 | | |
161 | | - Capability to set Waffle mode to ASM in closed-loop (SOUL-AO) |
162 | | - Capability to set an offset shape to ASM in closed-loop for NCPA characterization/removal |
163 | | |
164 | | - Connection b/w scientific camera control electronics to scientific camera workstation in the control room on level 2. |
165 | | - access to the server room. support will be needed to install the instrument workstation (1U Dell server) and to install the scientific camera workstation in the control room on level 2 |
166 | | |
167 | | |
168 | | |
169 | | 8.4 Installation interfaces |
170 | | All the checks to verify the feasibility of the installation procedure of SHARK-NIR have been performed on the CAD model “SHARK Installation Final.stp”. For installation purposes, the requirements to LBTO are: |
171 | | |
172 | | • Remove the door of the Nystrom LBTI top hatch (SX side). |
173 | | • Installation of the rotator work platform at the central bent focal station, SX side. |
174 | | • Use of the dome crane, to lower the subsystems of SHARK-NIR (as described in AD6) through the hatch in the UIAP LBTI platform and from the M1 side. |
175 | | • Operator to move the crane. |
176 | | • General assistance during the mounting phases. |
177 | | |
178 | | 8.5 Electrical interfaces |
179 | | SHARK-NIR electronics design is reported in AD5. |
180 | | - Summary of required space in the rack (total space: 13U): |
181 | | o The motor control unit dimensions are 483mm (width) x 133,35mm (height) x 525mm (depth) (also indicated as 19‘‘ × 3U × 525 mm) |
182 | | o The dimensions of the Lake Shore 336 temperature controller are 435 mm W × 89 mm H (2U) × 368 mm D (17 in × 3.5 in × 14.5 in) |
183 | | o Custom realized box: (2U in height) may contain the 2 light sources and their power supply, a motorized linear stage (M-403.2DG from Physik Instrumente), a small optical system consisting of 2 lenses and 1 filter to select the light to inject into the integrating sphere of SHARK-NIR (broadband or multi-narrow bands), the TT camera power supply and the power switches board (relais board) |
184 | | o DM electronics is contained in a 19” × 4U |
185 | | o WFC BCU housing: 19” × 2U (TBC) |
186 | | - Power requirement (total Watt dissipation: 700W): |
187 | | o The motor control unit maximum power consumptions is ~350W. |
188 | | o The Camera temperature controller maximum power consumption is of the order of ~100W. Its power requirement is 100, 120, 220, 240 VAC, ±10%, 50 or 60 Hz, 250 VA. |
189 | | o The C-RED2 camera needs a 12V power supply and a commercial “relais” board controllable through Ethernet, is required, to power the power supply, which has a power dissipation of the order of 10W. |
190 | | Custom box: power to be dissipated of the order of 100W |
191 | | o DM electronics power consumption is 150W. |
192 | | o WFC BCU: 24Vdc (48Vdc is also possible upon request) and the estimated power consumption is ~15W |
193 | | The agreed cabinet to allocate the above described electronics is rack 2, referring to Figure 6. The space reserved to SHARK-NIR electronics is the lowest area of the cabinet. |
194 | | |
195 | | |
196 | | Figure 6: the agreed cabinet for SHARK-NIR electronic is #2. |
197 | | 8.6 Thermal interfaces |
198 | | - Cooling: |
199 | | o Daily refill of the cryostat: one LN2 refill per day is required (~10 liters). The camera LN2 hold time is of the order of 28 hours (computed in very conservative conditions, see AD7), giving a reasonable margin on the refilling time. |
200 | | o Liquid cooling of the technical camera C-RED 2 from First Light (through LBTO glycol system, described in RD9): |
201 | | Max temperature: 35°C |
202 | | Min Temperature: dew point |
203 | | Pressure: 10 bar max |
204 | | Cooling capacity: 100W minimum |
205 | | Flow rate: > 0.5 L/min |
206 | | Max 50% ethylen glycol aqueous solution ; 50% distilled water or deionized water |
207 | | |
208 | | 8.7 Other interfaces |
209 | | - Air Flow: |
210 | | o A clean air flow with a maximum required flux of 0.5 m3/min to keep SHARK-NIR optical bench on a slight over-pressure with respect to the outer environment. |
211 | | 8.8 Logistics |
212 | | 8.8.1 Connections |
213 | | An Ethernet cable should reach the computer rooms located at level 2. |
214 | | 8.8.2 Storage |
215 | | Space (TBD) for storage should be made available at 3L. |
| 159 | === Reminders |
| 160 | - check if all the installation of interfaces is mentioned and in the right places. if LBTO support is needed (crew, crane support, etc.), mention those. |
| 161 | - make sure if all the support from LBTI and iLOCATOR team are mentioned clearly (related to the installation of electronics in their cabinets, sharing space, access permissions, IP addresses, etc.) |
| 162 | - need emergency stop buttons in SHARK-NIR? If so, need to integrate them into the LBT control system? |
| 163 | - check if all the electronics related support and requirements are mentioned. |
| 164 | - check if all okay for the LN2 fill and glycol/cooling water flow, etc. |