137 | | ||P1.6||[wiki:/docs/CommissioningPlan/P1.5 SCICAM refocussing]||1.5||C1|| || |
138 | | ||P1.7||[wiki:/docs/CommissioningPlan/P1.11 Science detector calibrations]||0.5||C3 + C4||P1.5 should be completed.|| |
139 | | ||P1.8||[wiki:/docs/CommissioningPlan/P1.7 Motor/light sources functional verification, filter artifacts/defects verification, and NCPA & internal tip-tilt loop verification]||1.5||C1||P1.7 should be completed.|| |
140 | | ||P1.9||[wiki:/docs/CommissioningPlan/P1.12 Testing of SCICAM image grabbing by SOUL-AO]||0.5||C3|| || |
141 | | ||P1.10||[wiki:/docs/CommissioningPlan/P1.8 Internal alignment verification]||1||C1|| || |
142 | | ||P1.11||[wiki:/docs/CommissioningPlan/P1.9 Instrument re-alignment]||1 - 6||C1||The duration of this activity, if needed, can be between 1 day to a maximum of 6 days.|| |
143 | | ||P1.12||[wiki:/docs/CommissioningPlan/P1.10 Verification of the contrast for coronagraphic masks]||1||C1||P1.10 (and if needed P1.11) should be completed. || |
| 137 | ||P1.6||[wiki:/docs/CommissioningPlan/P1.6 SCICAM refocussing]||1.5||C1|| || |
| 138 | ||P1.7||[wiki:/docs/CommissioningPlan/P1.7 Science detector calibrations]||0.5||C3 + C4||P1.5 should be completed.|| |
| 139 | ||P1.8||[wiki:/docs/CommissioningPlan/P1.8 Motor/light sources functional verification, filter artifacts/defects verification, and NCPA & internal tip-tilt loop verification]||1.5||C1||P1.7 should be completed.|| |
| 140 | ||P1.9||[wiki:/docs/CommissioningPlan/P1.9 Testing of SCICAM image grabbing by SOUL-AO]||0.5||C3|| || |
| 141 | ||P1.10||[wiki:/docs/CommissioningPlan/P1.10 Internal alignment verification]||1||C1|| || |
| 142 | ||P1.11||[wiki:/docs/CommissioningPlan/P1.11 Instrument re-alignment]||1 - 6||C1||The duration of this activity, if needed, can be between 1 day to a maximum of 6 days.|| |
| 143 | ||P1.12||[wiki:/docs/CommissioningPlan/P1.12 Verification of the contrast for coronagraphic masks]||1||C1||P1.10 (and if needed P1.11) should be completed. || |