Changes between Version 254 and Version 255 of docs/CommissioningPlan


Ignore:
Timestamp:
04/22/22 15:16:47 (3 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan

    v254 v255  
    2727
    2828== Introduction ==
    29 This commissioning planning document lays out and details the activities needed to bring SHARK-NIR online for __single-eye shared-risk scientific exploitation__ (the binocular observations with SHARK-VIS or trinocular with SHARK-VIS & LBTI are out of the scope of this commissioning plan). The document incorporates activities starting from the unpacking of the boxes at the LBT mountain bay to the early science (or science verification) at its final destination on the LBT platform. Although called the commissioning document, it lists the pre-commissioning, commissioning, and science verification activities. The activities are classified into three phases.
     29This commissioning planning document lays out and details the activities needed to bring SHARK-NIR online for __single-eye shared-risk scientific exploitation__ (the binocular observations with SHARK-VIS or trinocular with SHARK-VIS & LBTI are out of the scope of this commissioning plan). The document incorporates activities starting from the unpacking of the boxes at the LBT mountain bay to the early science (or science verification) at its final destination on the LBT platform. Although called the commissioning document, it lists the pre-commissioning, commissioning, and science verification activities. The activities are classified into four phases.  Phases 1 and 2 are purely daytime activities. Phases 3 and 4 are nighttime activities. It is to be noted that Phase 3 activities are classified into observing cases (OC#, see the table below) and '''not''' according to the observing modes (direct imaging, coronagraphic imaging, long-slit spectroscopy) anymore. This allows commencing Phase 4 (science verification) of those observing cases immediately after the completion of the respective Phase 3 commissioning run. See below for more details.
    3030
    3131 **Phase 1**: We start by inspecting the boxes at LBT mountain bay, unpacking, and installing the instrument at the mountain lab (clean room) for alignment verification and functionality checks. All of these are daytime activities. This forms the content of the __PSR-09 Preliminary Laboratory Integration & Test (I&T) Procedure__ (at LBT). [Pre-commissioning: Unpack, assemble, and clean-room verification]
     
    3333 **Phase 2**: The activities start from the installation of SHARK-NIR at the SX central bent Gregorian focus of LBT, followed by preliminary functional checks, aligning SHARK-NIR to the telescope (daytime), and daytime closed dome engineering/technical testing. All of these are daytime activities. [Pre-commissioning: Installation, functional checks, and closed-dome testing]
    3434
    35  **Phase 3**: The nighttime commissioning commences, starting from sending preset to the telescope to testing individual SHARK-NIR observation cases for performance to the total SHARK-NIR performance. The final form of the SHARK-NIR software, observing blocks, data-reduction pipeline, etc., will be tested for all the observing cases of the instrument. All the activities are at nighttime. Very few daytime activities are anticipated. Science verification of a set of observing cases will be performed immediately after the completion of a set of essential nighttime activities. [Commissioning and Science Verification]
     35 **Phase 3**: Phase 3 commences the nighttime commissioning, starting from sending preset to the telescope to testing individual SHARK-NIR observation modes for performance to the total SHARK-NIR performance. The final form of the SHARK-NIR software, observing blocks, data-reduction pipeline, etc., will be tested for all the observing cases of the instrument. All the activities are at nighttime. However, some daytime activities may be anticipated as well. There will be a common run (Run 1) to test the basic common requirements for each of the observing cases. Run 2-5 blocks represent the nighttime technical commissioning of a set of 17 observing cases. After the completion of each of these runs, SHARK-NIR will be ready for Phase 4 (science verification) of the respective observing cases. [Commissioning]
     36
     37 **Phase 4**: SHARK-NIR is ready for the final phase of the commissioning - the early science (or science verification) observations. The final performance of the SHARK-NIR will be analyzed using the data from this run. All the activities are at nighttime. By the end of this phase, SHARK-NIR is ready for single-eye shared-risk scientific exploitation. [Early Science or Science Verification]
     38
    3639
    3740
     
    116119
    117120
     121
    118122== Commissioning Activity ==
    119 In this section, all the commissioning activities are listed in chronological order. If you click on the individual activity, you can find more details. __8 hours is considered as the duration of a day or night__. Of course, depending on the month of the year, make sure to estimate the correct number of days/nights required at the LBT. Each table below corresponds to a trip to LBT.
     123In this section, all the commissioning activities are listed in chronological order. If you click on the individual activity, you can find more details. __8 hours is considered as the duration of a day__. Of course, depending on the month of the year, make sure to estimate the correct number of days/nights required at the LBT. Each table below corresponds to a trip to LBT.
    120124
    121125From commissioning experience at the LBT, for the daytime activities at the telescope platform, the telescope may be handed over around 09:00 am local time. And, the SHARK-NIR team needs to hand over the telescope to LBT ~2 hours before the sunset (unless we have the first half of the night or full night and to be negotiated with the telescope operator). As a general rule, the SHARK-NIR team will be working also on the weekends when at the summit. Of course, if LBTO support is required, this will be communicated with the LBTO mountain manager well in advance. Note that the duration of the individual activities mentioned in this document will not match that of AD4 for the same activities.
     
    168172
    169173=== Phase 3 (Commissioning)===
    170 '''SHARK-NIR Location''': LBT platform. All activities are __nightime__. Some daytime support (within SHARK-NIR) may be required. Also, the SHARK-NIR software, SHINS, is expected to be almost ready to be tested.
    171 
    172 Phase 3 is further divided into 5 runs. Run 1 consists of essential common activities essential for every observing case. This will be the first to be tested on-sky. Run 2-5 blocks represent the nighttime technical commissioning of a set of 17 observing cases. For each of the observing cases, only one target will be tested. The contrast obtained from the data will be used as the merit function or success criterion. If contrast is not an option, a similar (or another) merit function will be used. After the completion of each of these runs, SHARK-NIR will be ready for Phase 4 (science verification) of the respective observing cases.
    173 
    174 It is important to note that __Run 2-5 are interchangeable__. It is currently sorted to have the software complexity in the increasing order and also considering the science interest. Note that "Run N" does not mean that it is the Nth visit to the observatory. For example, Run 1 can be completed in 1 or 2 visits to the observatory, depending on the allotted time. Note also that, for individual runs (2-5), the time taken for other basic activities (such as moving from one target to another, setting up the telescope, closing the AO loop, etc.) are not explicitly mentioned in the table. For example, we anticipate, it may take between 10-20 minutes to move and set the telescope and close the AO loop from one target to another (numbers from the LUCI overheads table). This extra duration required will be mostly covered within the 20% contingency and/or the rounding up of the total nights.
     174'''SHARK-NIR Location''': LBT platform. All activities are __nightime__. Some daytime (within SHARK-NIR) may be required. Also, the SHARK-NIR software, SHINS, is expected to be almost ready to be tested.
     175
     176Phase 3 is further divided into 4 runs (Com-Run-#), each corresponding to a trip to LBT. Com-Run-1 consists of essential common activities essential for every observing case. This will be the first to be tested on-sky. Com-Run-2 to Com-Run-4  are__interchangeable__. It is currently sorted to have the software complexity in the increasing order and also considering the science interest. By the end of these 4 runs, all the SHARK-NIR observing cases will be verified on sky. For each of the observing cases, one (or a maximum of two) target(s) will be tested. The contrast obtained from the data will be used as the merit function or success criterion. If contrast is not an option, a similar (or another) merit function will be used. After the completion of each of these runs, SHARK-NIR will be ready for Phase 4 (science verification) of the respective observing cases.
     177
     178Note that, for individual runs (2-4), the time taken for other basic activities (such as moving from one target to another, setting up the telescope, closing the AO loop, etc.) are not explicitly mentioned in the table. For example, we anticipate that it may take between 10-20 minutes to move and set the telescope and close the AO loop from one target to another (numbers from the LUCI overheads table). This extra duration required will be mostly covered within the 15% contingency and/or the rounding up of the total nights.
    175179
    176180Every evening of the nighttime commissioning, all the required calibrations (including dark, bias, flat-field, etc. for all the filters required) will be taken using the SHARK-NIR calibration unit.
     
    183187
    184188**__Com-Run-1__**
    185 ||'''#'''||'''Activity Name / Observing Case'''||'''Duration (hours)'''||'''Seeing Conditions'''||'''Category'''||'''Note'''||
    186 || P3.1 ||[wiki:/docs/CommissioningPlan/P3.2 Telescope control – sending preset, telescope mode, offset, and focal plane geometry estimation]||3||medium / bad||C5|| ||
    187 || P3.3 ||[wiki:/docs/CommissioningPlan/P3.3 SOUL-AO verification]||6||good / medium||C5 + C7|| ||
    188 || P3.4 ||[wiki:/docs/CommissioningPlan/P3.4 Pupil alignment] (for checking the pupil positon, and working of the script)||2||bad||C5 + C6|| ||
    189 || P3.5 ||[wiki:/docs/CommissioningPlan/P3.5 PSF Alignment]||3||good / medium||C5 + C6|| ||
    190 || P3.6 ||[wiki:/docs/CommissioningPlan/P3.6 Verify the ADC rotation on sky]||4||medium / bad||C5|| ||
    191 || P3.7 ||[wiki:/docs/CommissioningPlan/P3.7 Checking field-stabilized mode/bearing rotation service]||2||bad||C5|| ||
    192 || P3.8 ||[wiki:/docs/CommissioningPlan/P3.8 Internal TT loop working and performance] (in different magnitude)||3||good / medium||C5 + C7|| ||
    193 || P3.9 ||[wiki:/docs/CommissioningPlan/P3.9 NCPA working and performance & checking for pupil shifts]||8||medium (up to 1")||C5 + C7|| ||
    194 || P3.10 ||[wiki:/docs/CommissioningPlan/P3.10 Check the acquisition procedure]||2||medium||C5|| ||
    195 || P3.11 ||[wiki:/docs/CommissioningPlan/P3.11 Sky background]||2||bad||C5 + C6|| ||
    196 || P3.12 ||[wiki:/docs/CommissioningPlan/P3.12 Astrometry plate scale and orientation]||2||good / medium||C5 + C6|| ||
    197 || P3.13||[wiki:/docs/CommissioningPlan/P3.13 Distortion map]||2||good / medium||C5 + C6|| ||
     189||'''#'''||'''Activity Name / Observing Case'''||'''Duration (hours)'''||'''Seeing Conditions'''||'''Category'''||
     190|| P3.1 ||[wiki:/docs/CommissioningPlan/P3.2 Telescope control – sending preset, telescope mode, offset, and focal plane geometry estimation]||3||medium / bad||C5||
     191|| P3.3 ||[wiki:/docs/CommissioningPlan/P3.3 SOUL-AO verification]||6||good / medium||C5 + C7||
     192|| P3.4 ||[wiki:/docs/CommissioningPlan/P3.4 Pupil alignment] (for checking the pupil positon, and working of the script)||2||bad||C5 + C6||
     193|| P3.5 ||[wiki:/docs/CommissioningPlan/P3.5 PSF Alignment]||3||good / medium||C5 + C6||
     194|| P3.6 ||[wiki:/docs/CommissioningPlan/P3.6 Verify the ADC rotation on sky]||4||medium / bad||C5||
     195|| P3.7 ||[wiki:/docs/CommissioningPlan/P3.7 Checking field-stabilized mode/bearing rotation service]||2||bad||C5||
     196|| P3.8 ||[wiki:/docs/CommissioningPlan/P3.8 Internal TT loop working and performance] (in different magnitude)||3||good / medium||C5 + C7||
     197|| P3.9 ||[wiki:/docs/CommissioningPlan/P3.9 NCPA working and performance & checking for pupil shifts]||8||medium (up to 1")||C5 + C7||
     198|| P3.10 ||[wiki:/docs/CommissioningPlan/P3.10 Check the acquisition procedure]||2||medium||C5||
     199|| P3.11 ||[wiki:/docs/CommissioningPlan/P3.11 Sky background]||2||bad||C5 + C6||
     200|| P3.12 ||[wiki:/docs/CommissioningPlan/P3.12 Astrometry plate scale and orientation]||2||good / medium||C5 + C6||
     201|| P3.13||[wiki:/docs/CommissioningPlan/P3.13 Distortion map]||2||good / medium||C5 + C6||
    198202|| OC1||Direct imaging - pupil stabilized||3||medium / bad||C5 + C7||
    199203|| OC2||DBI - Direct imaging - pupil stabilized||3||medium / bad||C5 + C7||
    200204|| OC3||Direct imaging - field stabilized||3||medium / bad||C5 + C7||
    201205|| OC4||DBI - Direct imaging - field stabilized||3||medium / bad||C5 + C7||
    202 || || **Total duration without contingency**|| 51 hours = ~6 nights || Considered 1 night = 9 hours||
    203 || || **Total duration with 15% contingency**||**7** nights||
     206|| || Total duration without contingency|| 51 hours = 5.67 nights ||Assumption: 1 night = 9 hours||
     207|| || **Total duration with 15% contingency (rounded up)**||**7** nights||
    204208
    205209'' Phase 4 science verification of the observing cases (1-4) can start after Com-Run-1. ''
    206210
    207211**__Com-Run-2__**
    208 ||'''#'''||'''Activity Name / Observing Case'''||'''Duration (hours)'''||'''Seeing Conditions'''||'''Category'''||'''Note'''||
    209 ||Test||Test / Correction following previous Run #||4||bad||C5||
     212||'''#'''||'''Activity Name / Observing Case'''||'''Duration (hours)'''||'''Seeing Conditions'''||'''Category'''||
     213||Test||Test / Correction following previous Com-Run-#||4||bad||C5||
    210214||P3.4 ||[wiki:/docs/CommissioningPlan/P3.4 Pupil alignment] (for GL and FQPM)||1||bad||C5 + C6||
    211215||P3.5||[wiki:/docs/CommissioningPlan/P3.5 PSF Alignment] (for GL and FQPM)||2||good / medium||C5 + C6||
     
    222226
    223227**__Com-Run-3__**
    224 ||'''#'''||'''Activity Name / Observing Case'''||'''Duration (hours)'''||'''Seeing Conditions'''||'''Category'''||'''Note'''||
    225 ||Test||Test / Correction following previous Run #||4||bad||C5||
     228||'''#'''||'''Activity Name / Observing Case'''||'''Duration (hours)'''||'''Seeing Conditions'''||'''Category'''||
     229||Test||Test / Correction following previous Com-Run-#||4||bad||C5||
    226230||P3.4 ||[wiki:/docs/CommissioningPlan/P3.4 Pupil alignment] (for SP-1, SP-2, SP-3)||1||bad||C5 + C6||
    227231||P3.5 ||[wiki:/docs/CommissioningPlan/P3.5 PSF Alignment] (for SP-1, SP-2, SP-3)||2||good / medium||C5 + C6||
     
    240244
    241245**__Com-Run-4__**
    242 ||'''#'''||'''Activity Name / Observing Case'''||'''Duration (hours)'''||'''Seeing Conditions'''||'''Category'''||'''Note'''||
    243 ||Test||Test / Correction following previous Run #||3||bad||C5||
     246||'''#'''||'''Activity Name / Observing Case'''||'''Duration (hours)'''||'''Seeing Conditions'''||'''Category'''||
     247||Test||Test / Correction following previous Com-Run-#||3||bad||C5||
    244248||P3.5 ||[wiki:/docs/CommissioningPlan/P3.5 PSF Alignment] (for SLIT-1 and SLIT-2)||2||good / medium||C5 + C6||
    245249||P3.18 ||[wiki:/docs/CommissioningPlan/P3.18 Center the slit]||8||medium / bad||C5||
     
    259263Every evening of the nighttime commissioning, all the required calibrations (including dark, bias, flat-field, etc. for all the filters required) will be taken using the SHARK-NIR calibration unit.
    260264**__SV-Run-1__**
    261 ||'''#'''||'''Activity Name / Observing Case'''||'''Duration (hours)'''||'''Seeing Conditions'''||'''Category'''||'''Note'''||
     265||'''#'''||'''Activity Name / Observing Case'''||'''Duration (hours)'''||'''Seeing Conditions'''||'''Category'''||
    262266||P4.1||[wiki:/docs/CommissioningPlan/P4.1 Exo-planet: Giant planets and brown dwarfs in SFR, stellar associations, & young open clusters]||8||C8||
    263267||P4.2||[wiki:/docs/CommissioningPlan/P4.2 Exo-planet: Astrometry]||1||C8||