Changes between Version 253 and Version 254 of docs/CommissioningPlan
- Timestamp:
- 04/22/22 13:27:30 (3 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan
v253 v254 200 200 || OC3||Direct imaging - field stabilized||3||medium / bad||C5 + C7|| 201 201 || OC4||DBI - Direct imaging - field stabilized||3||medium / bad||C5 + C7|| 202 || || **Total duration without contingency**|| hours = nights || Considered 1 night = 8hours||203 || || **Total duration with 20% contingency (rounded up)**||**8.55** nights||202 || || **Total duration without contingency**|| 51 hours = ~6 nights || Considered 1 night = 9 hours|| 203 || || **Total duration with 15% contingency**||**7** nights|| 204 204 205 205 '' Phase 4 science verification of the observing cases (1-4) can start after Com-Run-1. ''