Changes between Version 253 and Version 254 of docs/CommissioningPlan


Ignore:
Timestamp:
04/22/22 13:27:30 (3 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan

    v253 v254  
    200200|| OC3||Direct imaging - field stabilized||3||medium / bad||C5 + C7||
    201201|| OC4||DBI - Direct imaging - field stabilized||3||medium / bad||C5 + C7||
    202 || || **Total duration without contingency**|| hours = nights || Considered 1 night = 8 hours||
    203 || || **Total duration with 20% contingency (rounded up)**||**8.55** nights||
     202|| || **Total duration without contingency**|| 51 hours = ~6 nights || Considered 1 night = 9 hours||
     203|| || **Total duration with 15% contingency**||**7** nights||
    204204
    205205'' Phase 4 science verification of the observing cases (1-4) can start after Com-Run-1. ''