Changes between Version 249 and Version 250 of docs/CommissioningPlan


Ignore:
Timestamp:
04/22/22 12:36:01 (3 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan

    v249 v250  
    136136||P1.11||[wiki:/docs/CommissioningPlan/P1.9 Instrument re-alignment]||1 - 6||C1||The duration of this activity, if needed, can be between 1 day to a maximum of 6 days.||
    137137||P1.12||[wiki:/docs/CommissioningPlan/P1.10 Verification of the contrast for coronagraphic masks]||1||C1||P1.10 (and if needed P1.11) should be completed. ||
    138 || || Total without contingency (if re-alignment is __not__ required)||**11 days**  ||
     138|| || Total without contingency (if re-alignment is __not__ required)||11 days  ||
    139139|| || Total with 10% contingency (if re-alignment is __not__ required)||**12 days** ||
    140 || || Total without contingency (if re-alignment is required)||**12-17 days** ||
     140|| || Total without contingency (if re-alignment is required)||12-17 days ||
    141141|| || Total with 10% contingency (if re-alignment is required)||**13-19 days** ||