124 | | '''SHARK-NIR Location''': LBT mountain bay and clean room. Some of the activities may run in parallel. All the activities are daytime. In the cleanroom, usually, there are no restrictions on daytime or nighttime activity. |
125 | | ||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (days)'''||'''Category'''|| |
126 | | ||P1.1||[wiki:/docs/CommissioningPlan/P1.1 Inspection of the closed boxes]||Day||0.5||C1|| |
127 | | ||P1.2||[wiki:/docs/CommissioningPlan/P1.2 Opening of boxes in LBT Hall, inspection of the contents and installation of units on their handlings]||Day||1||C1|| |
128 | | ||P1.3||[wiki:/docs/CommissioningPlan/P1.3 Installation of SHARK-NIR HW and electronics in clean room]||Day||1.5||C1|| |
129 | | ||P1.4||[wiki:/docs/CommissioningPlan/P1.4 Cable in the instrument, power on, install workstations, and connect to LBT network]||Day||1||C1|| |
130 | | ||P1.5||[wiki:/docs/CommissioningPlan/P1.5 SW checks and motors initializations]||Day||1||C1|| |
131 | | ||P1.6||[wiki:/docs/CommissioningPlan/P1.6 Cryostat cool down]||Day||0.5||C1|| |
132 | | ||P1.7||[wiki:/docs/CommissioningPlan/P1.7 Motor/light sources functional verification and filter artifacts/defects verification]||Day||1.5||C1|| |
133 | | ||P1.8||[wiki:/docs/CommissioningPlan/P1.8 Internal alignment verification]||Day||4||C1|| |
134 | | ||P1.9||[wiki:/docs/CommissioningPlan/P1.9 Internal tip-tilt loop verification]||Day||1||C1|| |
135 | | ||P1.10||[wiki:/docs/CommissioningPlan/P1.10 NCPA routine verification]||Day||1||C1|| |
136 | | ||P1.11||[wiki:/docs/CommissioningPlan/P1.11 Science detector calibrations]||Day||1||C3 + C4|| |
137 | | ||P1.12||[wiki:/docs/CommissioningPlan/P1.12 Testing of SCICAM image grabbing by SOUL-AO]||Day||2||C3|| |
138 | | ||Total||(1.5 days of) contingency (15%) included within|| ||16|| || |
| 124 | '''SHARK-NIR Location''': LBT mountain bay and clean room. Some of the activities may run in parallel. All the activities are __daytime__. In the cleanroom, usually, there are no restrictions on daytime or nighttime activity. |
| 125 | ||'''Number'''||'''Activity Name'''||'''Duration (days)'''||'''Category'''||'''Note'''|| |
| 126 | ||P1.1||[wiki:/docs/CommissioningPlan/P1.1 Inspection of the closed boxes]||0.5||C1|| || |
| 127 | ||P1.2||[wiki:/docs/CommissioningPlan/P1.2 Opening of boxes in LBT Hall, inspection of the contents and installation of units on their handlings]||1||C1|| || |
| 128 | ||P1.3||[wiki:/docs/CommissioningPlan/P1.3 Installation of SHARK-NIR HW and electronics in clean room]||1.5||C1|| || |
| 129 | ||P1.4||[wiki:/docs/CommissioningPlan/P1.4 Cable in the instrument, power on, install workstations, connect to LBT network, and prepare for cryostat cooldown]||1||C1|| || |
| 130 | ||P1.5||[wiki:/docs/CommissioningPlan/P1.5 SW & HW functional checks and cryostat cooldown]||1||C1|| || |
| 131 | ||P1.6||[wiki:/docs/CommissioningPlan/P1.5 SCICAM refocussing]||1.5||C1|| || |
| 132 | ||P1.7||[wiki:/docs/CommissioningPlan/P1.11 Science detector calibrations]||0.5||C3 + C4||P1.5 should be completed.|| |
| 133 | ||P1.8||[wiki:/docs/CommissioningPlan/P1.7 Motor/light sources functional verification, filter artifacts/defects verification, and NCPA & internal tip-tilt loop verification]||1.5||C1||P1.7 should be completed.|| |
| 134 | ||P1.9||[wiki:/docs/CommissioningPlan/P1.12 Testing of SCICAM image grabbing by SOUL-AO]||0.5||C3|| || |
| 135 | ||P1.10||[wiki:/docs/CommissioningPlan/P1.8 Internal alignment verification]||1||C1|| || |
| 136 | ||P1.11||[wiki:/docs/CommissioningPlan/P1.9 Instrument re-alignment]||1 - 6||C1||The duration of this activity, if needed, can be between 1 day to a maximum of 6 days.|| |
| 137 | ||P1.12||[wiki:/docs/CommissioningPlan/P1.10 Verification of the contrast for coronagraphic masks]||1||C1||P1.10 (and if needed P1.11) should be completed. || |
| 138 | ||Total||Without contingency ||**11** (if re-alignment is not required) || |
| 139 | ||Total||Without contingency ||**12-17** (if re-alignment is required) || |
| 140 | ||Total||With 10% contingency ||**12** (if re-alignment is not required) || |
| 141 | ||Total||With 10% contingency ||**13-19** (if re-alignment is required) || |