  • docs/CommissioningPlan

    v241 v242  
    8181Each commissioning test/activity has a unified structure as follows:
    8282
    83 {{{
    84 Name of the commissioning activity
     83----
     84**Name of the commissioning activity**
    8585  - phase: states the phase of the commissioning (1/2/3/4)
    8686  - status: reports the current status of the test description (draft, final, complete)
     
    8989  - duration: estimates the time required to complete the test (the duration mentioned here is valid only for commissioning)
    9090
    91 Description
     91**Description**
    9292  - Contains a general description of the test
    9393
    94 Prerequisites
     94**Prerequisites**
    9595  - Lists items that must be in place before the test begins
    9696
    97 Procedure
     97**Procedure**
    9898  - Explains in detail how to execute the test
    9999
    100 Templates
     100**Templates**
    101101 - Mentions the templates to be used. If there are specific parameters, they are mentioned in brackets. For details on the templates mentioned, check AD9.
    102102
    103 Success Criteria
     103**Success Criteria**
    104104  - Enumerates the outcome associated with successful completion of the test
    105105
    106 Notes
     106**Notes**
    107107  - Additional supporting information
    108108
    109 LBTO Support
     109**LBTO Support**
    110110  - Mention if (and what) support is required from LBTO
    111111
    112 Date performed and by whom
     112**Date performed and by whom**
    113113  - Mentions who performed the test and when
    114 
    115 }}}
     114----