    9393||P1.2||[wiki:/docs/CommissioningPlan/P1.2 Opening boxes and their visual inspection]||Day||0.5||C1||crane operator to lift and move containers/boxes (mountain bay), 1-2 crew to support unpacking and moving||
    9494||P1.3||[wiki:/docs/CommissioningPlan/P1.3 Install the instrument in the cleanroom with its electronics cabinet]||Day||0.5||C1||crane operator to lift and move containers/boxes (mountain bay & cleanroom), 1-2 crew to support installation on the mechanical structure||
    95 ||P1.4||[wiki:/docs/CommissioningPlan/P1.4 Cable in the instrument, power on, install workstations, and connect to LBT network]||Day||0.5||C1||support to connect to LBT network, IT support to install/set the computers near Control room||
     95||P1.4||[wiki:/docs/CommissioningPlan/P1.4 Cable in the instrument, power on, install workstations, and connect to LBT network]||Day||0.5||C1||support to connect to LBT network, IT support to install/set the workstations in the proper location||
    9696||P1.5||[wiki:/docs/CommissioningPlan/P1.5 Start all the services and initialize all the motors]||Day||0.5||C1||-||
    9797||P1.6||[wiki:/docs/CommissioningPlan/P1.6 Cool down the cryostat]||Day||1||C1||Liquid N2 fill in the cleanroom||