Changes between Version 231 and Version 232 of docs/CommissioningPlan
- Timestamp:
- 01/24/22 11:12:46 (3 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan
v231 v232 121 121 ||P1.1||[wiki:/docs/CommissioningPlan/P1.1 Inspection of the closed boxes]||Day||0.5||C1||Crane operator (mountain bay) to lift and move stuff. 1-2 crew to support moving containers/boxes.|| 122 122 ||P1.2||[wiki:/docs/CommissioningPlan/P1.2 Opening of boxes in LBT Hall, inspection of the contents and installation of units on their handlings]||Day||1||C1||Crane operator (mountain bay) to lift and move stuff. 1-2 crew to support unpacking and moving.|| 123 ||P1.3||[wiki:/docs/CommissioningPlan/P1.3 Installation of SHARK-NIR HW and electronics in clean room]||Day|| 2||C1||Crane operator to lift and move stuff (mountain bay and/or cleanroom). 1-2 crew to support installation procedure (mountain bay and/or cleanroom). Access to the LBTO electronics cabinet where the motor rack of SHARK-NIR will be installed. Optical bench and access to the clean tent.||123 ||P1.3||[wiki:/docs/CommissioningPlan/P1.3 Installation of SHARK-NIR HW and electronics in clean room]||Day||1.5||C1||Crane operator to lift and move stuff (mountain bay and/or cleanroom). 1-2 crew to support installation procedure (mountain bay and/or cleanroom). Access to the LBTO electronics cabinet where the motor rack of SHARK-NIR will be installed. Optical bench and access to the clean tent.|| 124 124 ||P1.4||[wiki:/docs/CommissioningPlan/P1.4 Cable in the instrument, power on, install workstations, and connect to LBT network]||Day||1||C1||IT support to install/set the workstations in the proper location, connect to the LBT network. LBTO SW support may be needed.|| 125 125 ||P1.5||[wiki:/docs/CommissioningPlan/P1.5 SW checks and motors initializations]||Day||1||C1||-|| 126 ||P1.6||[wiki:/docs/CommissioningPlan/P1.6 Cryostat cool down]||Day|| 1||C1||Liquid N2 refill is required in the cleanroom. Vacuum pump and support for cooling down the cryostat.||126 ||P1.6||[wiki:/docs/CommissioningPlan/P1.6 Cryostat cool down]||Day||0.5||C1||Liquid N2 refill is required in the cleanroom. Vacuum pump and support for cooling down the cryostat.|| 127 127 ||P1.7||[wiki:/docs/CommissioningPlan/P1.7 Motor/light sources functional verification and filter artifacts/defects verification]||Day||1.5||C1||Liquid N2 refill is required in the cleanroom.|| 128 128 ||P1.8||[wiki:/docs/CommissioningPlan/P1.8 Internal alignment verification]||Day||4||C1||Liquid N2 refill is required in the cleanroom.|| … … 131 131 ||P1.11||[wiki:/docs/CommissioningPlan/P1.11 Science detector calibrations]||Day||1||C3 + C4||Liquid N2 refill is required in the cleanroom.|| 132 132 ||P1.12||[wiki:/docs/CommissioningPlan/P1.12 Testing of SCICAM image grabbing by SOUL-AO]||Day||2||C3||Liquid N2 refill is required in the cleanroom. LBTO SW support may be required.|| 133 ||Total||( 2 days of) contingency (15%) included within|| ||17|| || ||133 ||Total||(1.5 days of) contingency (15%) included within|| ||16|| || || 134 134 135 135 === Phase 2 (Pre-commissioning)===