Changes between Version 22 and Version 23 of docs/CommissioningPlan


Ignore:
Timestamp:
10/06/20 11:58:40 (4 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan

    v22 v23  
    9393||P1.2||[wiki:/docs/CommissioningPlan/P1.2 Opening boxes and their visual inspection]||Day||0.5||C1||crane operator to lift and move containers/boxes (mountain bay), 1-2 crew to support unpacking and moving||
    9494||P1.3||[wiki:/docs/CommissioningPlan/P1.3 Install the instrument in the cleanroom with its electronics cabinet]||Day||0.5||C1||crane operator to lift and move containers/boxes (mountain bay & cleanroom), 1-2 crew to support installation on the mechanical structure||
    95 ||P1.4||[wiki:/docs/CommissioningPlan/P1.4 Cable in the instrument, power on, and connect to LBT network]||Day||0.5||C1||support to connect to LBT network, IT support to install/set the computers near Control room||
     95||P1.4||[wiki:/docs/CommissioningPlan/P1.4 Cable in the instrument, power on, install workstations, and connect to LBT network]||Day||0.5||C1||support to connect to LBT network, IT support to install/set the computers near Control room||
    9696||P1.5||[wiki:/docs/CommissioningPlan/P1.5 Start all the services and initialize all the motors]||Day||0.5||C1||-||
    9797||P1.6||[wiki:/docs/CommissioningPlan/P1.6 Cool down the cryostat]||Day||1||C1||Liquid N2 fill in the cleanroom||
     
    109109||P2.3||[wiki:/docs/CommissioningPlan/P2.3 TCS communication test]||Day||0.5||C2||Authorise SHARK-NIR, connecting to ASM+LBTI AO system, able to send preset, receiving LBT telemetry and details for the fitswriter, support from LBT SW team||
    110110||P2.4||[wiki:/docs/CommissioningPlan/P2.4 Align SHARK-NIR to the telescope]||Day||1+1||C2||working platform installed infont of the gregorian focal-station SX, Mounting RR on the SX side. Support from LBTI/Arcetri on running SOUL AO||
    111 ||P2.5||[wiki:/docs/CommissioningPlan/P2.5 Synergy with LBTI AO system test]||Day||0.5||C2||working platform installed infont of the gregorian focal-station SX, Mounting RR on the SX side. Support from LBTI/Arcetri on running SOUL AO||
     111||P2.5||[wiki:/docs/CommissioningPlan/P2.5 SOUL AO system test]||Day||0.5||C2||working platform installed infont of the gregorian focal-station SX, Mounting RR on the SX side. Support from LBTI/Arcetri on running SOUL AO||
    112112||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA]||Day||0.5||C3||Mounting RR on the SX side. Support from LBTI/Arcetri on running SOUL AO||
    113113||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Looking for filter defects/effects/features]||Day||0.5||C2||Mounting RR on the SX side. Support from LBTI/Arcetri on running SOUL AO||