Changes between Version 227 and Version 228 of docs/CommissioningPlan
- Timestamp:
- 01/20/22 14:08:34 (3 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan
v227 v228 128 128 ||P1.8||[wiki:/docs/CommissioningPlan/P1.8 Internal alignment verification]||Day||4||C1||Liquid N2 refill is required in the cleanroom.|| 129 129 ||P1.9||[wiki:/docs/CommissioningPlan/P1.9 Internal tip-tilt loop verification]||Day||1||C1||Liquid N2 refill is required in the cleanroom.|| 130 ||P1.10||[wiki:/docs/CommissioningPlan/P1.10 NCPA routine verification]||Day|| 0.5||C1||Liquid N2 refill is required in the cleanroom.||130 ||P1.10||[wiki:/docs/CommissioningPlan/P1.10 NCPA routine verification]||Day||1||C1||Liquid N2 refill is required in the cleanroom.|| 131 131 ||P1.11||[wiki:/docs/CommissioningPlan/P1.11 Science detector calibrations]||Day||1||C3 + C4||Liquid N2 refill is required in the cleanroom.|| 132 132 ||P1.12||[wiki:/docs/CommissioningPlan/P1.12 Testing of SCICAM image grabbing by SOUL-AO]||Day||2||C3||Liquid N2 refill is required in the cleanroom. LBTO SW support may be required.|| 133 ||Total||(2 days of) contingency (10%) included within|| ||16 || || ||133 ||Total||(2 days of) contingency (10%) included within|| ||16.5|| || || 134 134 135 135 === Phase 2 (Pre-commissioning)===