  • docs/CommissioningPlan

    v227 v228  
    128128||P1.8||[wiki:/docs/CommissioningPlan/P1.8 Internal alignment verification]||Day||4||C1||Liquid N2 refill is required in the cleanroom.||
    129129||P1.9||[wiki:/docs/CommissioningPlan/P1.9 Internal tip-tilt loop verification]||Day||1||C1||Liquid N2 refill is required in the cleanroom.||
    130 ||P1.10||[wiki:/docs/CommissioningPlan/P1.10 NCPA routine verification]||Day||0.5||C1||Liquid N2 refill is required in the cleanroom.||
     130||P1.10||[wiki:/docs/CommissioningPlan/P1.10 NCPA routine verification]||Day||1||C1||Liquid N2 refill is required in the cleanroom.||
    131131||P1.11||[wiki:/docs/CommissioningPlan/P1.11 Science detector calibrations]||Day||1||C3 + C4||Liquid N2 refill is required in the cleanroom.||
    132132||P1.12||[wiki:/docs/CommissioningPlan/P1.12 Testing of SCICAM image grabbing by SOUL-AO]||Day||2||C3||Liquid N2 refill is required in the cleanroom. LBTO SW support may be required.||
    133 ||Total||(2 days of) contingency (10%) included within|| ||16|| || ||
     133||Total||(2 days of) contingency (10%) included within|| ||16.5|| || ||
    134134
    135135=== Phase 2 (Pre-commissioning)===