    135135=== Phase 2 (Pre-commissioning)===
    136136'''SHARK-NIR Location''': LBT platform. Some of the activities may run in parallel. All daytime activities.
    137 ||'''Number'''||='''Activity Name'''=||'''Day / Night'''||'''Duration (days)'''||'''Category'''||'''LBTO Support'''||   
     137||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (days)'''||'''Category'''||'''LBTO Support'''||     
    138138||P2.0A||[wiki:/docs/CommissioningPlan/P2.0A Installation of SHARK-NIR on LBT platform]||Day||2(preparation) + 2(lift-off) + 1(contingency)||C2||Crew members' support for the preparation, lift-off, and installation of SHARK-NIR. Crane operator (cleanroom, mountain bay, LBT platform). Safety officer. Working platform installed in front of the Gregorian focal-station SX. Hatch door SX on the UIAP platform removed. Support for the installation of electronics in the LBTO cabinet. Kindly check the installation document, AD3, for more details.||
    139139||P2.0B||[wiki:/docs/CommissioningPlan/P2.0B Installation of SHARK-NIR electronics on LBT platform]||Day||2||C2||1-2 crew members' support for the preparation and installation of SHARK-NIR electronics. Safety officer. Kindly check the installation document, AD3, for more details.||