Changes between Version 225 and Version 226 of docs/CommissioningPlan


Ignore:
Timestamp:
01/18/22 15:15:16 (3 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan

    v225 v226  
    135135=== Phase 2 (Pre-commissioning)===
    136136'''SHARK-NIR Location''': LBT platform. Some of the activities may run in parallel. All daytime activities.
    137 ||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (days)'''||'''Category'''||='''LBTO Support'''=||   
     137||'''Number'''||='''Activity Name'''=||'''Day / Night'''||'''Duration (days)'''||'''Category'''||'''LBTO Support'''||   
    138138||P2.0A||[wiki:/docs/CommissioningPlan/P2.0A Installation of SHARK-NIR on LBT platform]||Day||2(preparation) + 2(lift-off) + 1(contingency)||C2||Crew members' support for the preparation, lift-off, and installation of SHARK-NIR. Crane operator (cleanroom, mountain bay, LBT platform). Safety officer. Working platform installed in front of the Gregorian focal-station SX. Hatch door SX on the UIAP platform removed. Support for the installation of electronics in the LBTO cabinet. Kindly check the installation document, AD3, for more details.||
    139139||P2.0B||[wiki:/docs/CommissioningPlan/P2.0B Installation of SHARK-NIR electronics on LBT platform]||Day||2||C2||1-2 crew members' support for the preparation and installation of SHARK-NIR electronics. Safety officer. Kindly check the installation document, AD3, for more details.||