    116116'''SHARK-NIR Location''': LBT mountain bay and clean room. Some of the activities may run in parallel. All daytime activities. In the cleanroom, usually, there are no restrictions on daytime or nighttime activity.
    117117||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (days)'''||'''Category'''||'''LBTO Support'''||                     
    118 ||P1.1||[wiki:/docs/CommissioningPlan/P1.1 Inspection of the boxes]||Day||0.5||C1||Crane operator (mountain bay) to lift and move stuff. 1-2 crew to support moving containers/boxes.||
    119 ||P1.2||[wiki:/docs/CommissioningPlan/P1.2 Opening boxes, their visual inspection, and mounting the units on the handling]||Day||1||C1||Crane operator (mountain bay) to lift and move stuff. 1-2 crew to support unpacking and moving.||
    120 ||P1.3||[wiki:/docs/CommissioningPlan/P1.3 Complete the installation of SHARK-NIR in the cleanroom with its electronics cabinet]||Day||1.5||C1||Crane operator to lift and move stuff (mountain bay and/or cleanroom). 1-2 crew to support installation procedure (mountain bay and/or cleanroom). Access to the LBTO electronics cabinet where the motor rack of SHARK-NIR will be installed. Optical bench and access to the clean tent.||
     118||P1.1||[wiki:/docs/CommissioningPlan/P1.1 Inspection of the closed boxes]||Day||0.5||C1||Crane operator (mountain bay) to lift and move stuff. 1-2 crew to support moving containers/boxes.||
     119||P1.2||[wiki:/docs/CommissioningPlan/P1.2 Opening of boxes in LBT Hall, inspection of the content and installation on units on their handlings]||Day||1||C1||Crane operator (mountain bay) to lift and move stuff. 1-2 crew to support unpacking and moving.||
     120||P1.3||[wiki:/docs/CommissioningPlan/P1.3 Installation of SHARK-NIR HW and electronics in clean room]||Day||1.5||C1||Crane operator to lift and move stuff (mountain bay and/or cleanroom). 1-2 crew to support installation procedure (mountain bay and/or cleanroom). Access to the LBTO electronics cabinet where the motor rack of SHARK-NIR will be installed. Optical bench and access to the clean tent.||
    121121||P1.4||[wiki:/docs/CommissioningPlan/P1.4 Cable in the instrument, power on, install workstations, and connect to LBT network]||Day||1||C1||IT support to install/set the workstations in the proper location, connect to the LBT network. LBTO SW support may be needed.||
    122 ||P1.5||[wiki:/docs/CommissioningPlan/P1.5 Start all the services and initialize all the motors]||Day||1||C1||-||
    123 ||P1.6||[wiki:/docs/CommissioningPlan/P1.6 Cool down the cryostat]||Day||1||C1||Liquid N2 refill is required in the cleanroom. Vacuum pump and support for cooling down the cryostat.||
    124 ||P1.7||[wiki:/docs/CommissioningPlan/P1.7 Check the working of the internal NCPA routine]||Day||0.5||C1||Liquid N2 refill is required in the cleanroom.||
    125 ||P1.8||[wiki:/docs/CommissioningPlan/P1.8 Verification of the internal alignment of the instrument]||Day||4||C1||Liquid N2 refill is required in the cleanroom.||
    126 ||P1.9||[wiki:/docs/CommissioningPlan/P1.9 Check the working of the internal tip-tilt loop]||Day||1||C1||Liquid N2 refill is required in the cleanroom.||
    127 ||P1.10||[wiki:/docs/CommissioningPlan/P1.10 Verification of the operability of the motors & light sources and looking for filter defects/artifacts]||Day||1.5||C1||Liquid N2 refill is required in the cleanroom.||
     122||P1.5||[wiki:/docs/CommissioningPlan/P1.5 SW checks and motors initializations]||Day||1||C1||-||
     123||P1.6||[wiki:/docs/CommissioningPlan/P1.6 Cryostat cool down]||Day||1||C1||Liquid N2 refill is required in the cleanroom. Vacuum pump and support for cooling down the cryostat.||
     124||P1.7||[wiki:/docs/CommissioningPlan/P1.7 NCPA routine verification]||Day||0.5||C1||Liquid N2 refill is required in the cleanroom.||
     125||P1.8||[wiki:/docs/CommissioningPlan/P1.8 Internal alignment verification]||Day||4||C1||Liquid N2 refill is required in the cleanroom.||
     126||P1.9||[wiki:/docs/CommissioningPlan/P1.9 Internal tip-tilt loop verification]||Day||1||C1||Liquid N2 refill is required in the cleanroom.||
     127||P1.10||[wiki:/docs/CommissioningPlan/P1.10 Motor/light sources functional verification and filter artifacts/defects verification]||Day||1.5||C1||Liquid N2 refill is required in the cleanroom.||
    128128||P1.11||[wiki:/docs/CommissioningPlan/P1.11 Science detector calibrations]||Day||1||C1 + C4||Liquid N2 refill is required in the cleanroom.||
    129129||P1.12||[wiki:/docs/CommissioningPlan/P1.12 Testing of SCICAM image grabbing by SOUL-AO]||Day||2||C1||Liquid N2 refill is required in the cleanroom. LBTO SW support may be required.||
     
    133133'''SHARK-NIR Location''': LBT platform. Some of the activities may run in parallel. All daytime activities.
    134134||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (days)'''||'''Category'''||'''LBTO Support'''||     
    135 ||P2.0A||[wiki:/docs/CommissioningPlan/P2.0A Installation of the SHARK-NIR at LBT platform - 1]||Day||2(preparation) + 2(lift-off) + 1(contingency)||C2||Crew members' support for the preparation, lift-off, and installation of SHARK-NIR. Crane operator (cleanroom, mountain bay, LBT platform). Safety officer. Working platform installed in front of the Gregorian focal-station SX. Hatch door SX on the UIAP platform removed. Support for the installation of electronics in the LBTO cabinet. Kindly check the installation document, AD3, for more details.||
    136 ||P2.0B||[wiki:/docs/CommissioningPlan/P2.0B Installation of the SHARK-NIR at LBT platform - 2]||Day||2||C2||1-2 crew members' support for the preparation and installation of SHARK-NIR electronics. Safety officer. Kindly check the installation document, AD3, for more details.||
    137 ||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Activating the instrument, basic check, initiate cryostat cool down]||Day||1||C3||Testing the working of the knob (motor/manual) controlling the cooldown. Liquid Nitrogen fill. Vacuum pump.||
     135||P2.0A||[wiki:/docs/CommissioningPlan/P2.0A Installation of SHARK-NIR on LBT platform]||Day||2(preparation) + 2(lift-off) + 1(contingency)||C2||Crew members' support for the preparation, lift-off, and installation of SHARK-NIR. Crane operator (cleanroom, mountain bay, LBT platform). Safety officer. Working platform installed in front of the Gregorian focal-station SX. Hatch door SX on the UIAP platform removed. Support for the installation of electronics in the LBTO cabinet. Kindly check the installation document, AD3, for more details.||
     136||P2.0B||[wiki:/docs/CommissioningPlan/P2.0B Installation of SHARK-NIR electronics on LBT platform]||Day||2||C2||1-2 crew members' support for the preparation and installation of SHARK-NIR electronics. Safety officer. Kindly check the installation document, AD3, for more details.||
     137||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Basic functionality and shutdown procedure test, cryostat cooldown]||Day||1||C3||Testing the working of the knob (motor/manual) controlling the cooldown. Liquid Nitrogen fill. Vacuum pump.||
    138138||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Instrument operability and functioning]||Day||2||C3||-||
    139139||P2.3||[wiki:/docs/CommissioningPlan/P2.3 TCS communication test]||Day||2||C3||Authorize SHARK-NIR. Permission to SX ASM and LBTI AO. Permission to send preset, receiving LBT telemetry (inc. the derotator trajectory) and details for the Fitswriter. Support from the LBT SW team.||
    140 ||P2.4||[wiki:/docs/CommissioningPlan/P2.4 Align SHARK-NIR to the telescope]||Day||3||C3||Working platform installed in front of the Gregorian focal-station SX, Argos swing arm and calibration source on SX side. Support from the LBTI team.||
     140||P2.4||[wiki:/docs/CommissioningPlan/P2.4 SHARK-NIR alignment to the telescope]||Day||3||C3||Working platform installed in front of the Gregorian focal-station SX, Argos swing arm and calibration source on SX side. Support from the LBTI team.||
    141141||P2.5||[wiki:/docs/CommissioningPlan/P2.5 SOUL AO system test]||Day||5||C3 + C4||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. If not the Argos swing arm, RR will be required on the SX side. AO support.||
    142 ||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA]||Day||8||C3 + C4||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. When not using the Argos swing arm and for different elevation angle tests, RR will be required on the SX side. AO support.||
     142||P2.6||[wiki:/docs/CommissioningPlan/P2.6 NCPA measurements]||Day||8||C3 + C4||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. When not using the Argos swing arm and for different elevation angle tests, RR will be required on the SX side. AO support.||
    143143||P2.65 / P3.12 / E1||[wiki:/docs/CommissioningPlan/P3.12 Star center Fourier mode images]||Day||2||C3||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. When not using the Argos swing arm and for different elevation angle tests, RR will be required on the SX side. AO support.||
    144144||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Checking pointing offset between SHARK-NIR and SOUL-AO]||Day||1||C3 + C4||Authorize SHARK-NIR on the SX side. RR mounted on the SX side. AO support.||
    145 ||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Redo science detector calibrations]||Day||1||C3 + C4||-||
     145||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Science detector calibrations (on the telescope)]||Day||1||C3 + C4||-||
    146146||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Cryostat warm up check]||Day||2||C3||-||
    147147||Total||(4 days of) contingency (15%) included within || ||34 days || || ||