118 | | ||P1.1||[wiki:/docs/CommissioningPlan/P1.1 Inspection of the boxes]||Day||0.5||C1||Crane operator (mountain bay) to lift and move stuff. 1-2 crew to support moving containers/boxes.|| |
119 | | ||P1.2||[wiki:/docs/CommissioningPlan/P1.2 Opening boxes, their visual inspection, and mounting the units on the handling]||Day||1||C1||Crane operator (mountain bay) to lift and move stuff. 1-2 crew to support unpacking and moving.|| |
120 | | ||P1.3||[wiki:/docs/CommissioningPlan/P1.3 Complete the installation of SHARK-NIR in the cleanroom with its electronics cabinet]||Day||1.5||C1||Crane operator to lift and move stuff (mountain bay and/or cleanroom). 1-2 crew to support installation procedure (mountain bay and/or cleanroom). Access to the LBTO electronics cabinet where the motor rack of SHARK-NIR will be installed. Optical bench and access to the clean tent.|| |
| 118 | ||P1.1||[wiki:/docs/CommissioningPlan/P1.1 Inspection of the closed boxes]||Day||0.5||C1||Crane operator (mountain bay) to lift and move stuff. 1-2 crew to support moving containers/boxes.|| |
| 119 | ||P1.2||[wiki:/docs/CommissioningPlan/P1.2 Opening of boxes in LBT Hall, inspection of the content and installation on units on their handlings]||Day||1||C1||Crane operator (mountain bay) to lift and move stuff. 1-2 crew to support unpacking and moving.|| |
| 120 | ||P1.3||[wiki:/docs/CommissioningPlan/P1.3 Installation of SHARK-NIR HW and electronics in clean room]||Day||1.5||C1||Crane operator to lift and move stuff (mountain bay and/or cleanroom). 1-2 crew to support installation procedure (mountain bay and/or cleanroom). Access to the LBTO electronics cabinet where the motor rack of SHARK-NIR will be installed. Optical bench and access to the clean tent.|| |
122 | | ||P1.5||[wiki:/docs/CommissioningPlan/P1.5 Start all the services and initialize all the motors]||Day||1||C1||-|| |
123 | | ||P1.6||[wiki:/docs/CommissioningPlan/P1.6 Cool down the cryostat]||Day||1||C1||Liquid N2 refill is required in the cleanroom. Vacuum pump and support for cooling down the cryostat.|| |
124 | | ||P1.7||[wiki:/docs/CommissioningPlan/P1.7 Check the working of the internal NCPA routine]||Day||0.5||C1||Liquid N2 refill is required in the cleanroom.|| |
125 | | ||P1.8||[wiki:/docs/CommissioningPlan/P1.8 Verification of the internal alignment of the instrument]||Day||4||C1||Liquid N2 refill is required in the cleanroom.|| |
126 | | ||P1.9||[wiki:/docs/CommissioningPlan/P1.9 Check the working of the internal tip-tilt loop]||Day||1||C1||Liquid N2 refill is required in the cleanroom.|| |
127 | | ||P1.10||[wiki:/docs/CommissioningPlan/P1.10 Verification of the operability of the motors & light sources and looking for filter defects/artifacts]||Day||1.5||C1||Liquid N2 refill is required in the cleanroom.|| |
| 122 | ||P1.5||[wiki:/docs/CommissioningPlan/P1.5 SW checks and motors initializations]||Day||1||C1||-|| |
| 123 | ||P1.6||[wiki:/docs/CommissioningPlan/P1.6 Cryostat cool down]||Day||1||C1||Liquid N2 refill is required in the cleanroom. Vacuum pump and support for cooling down the cryostat.|| |
| 124 | ||P1.7||[wiki:/docs/CommissioningPlan/P1.7 NCPA routine verification]||Day||0.5||C1||Liquid N2 refill is required in the cleanroom.|| |
| 125 | ||P1.8||[wiki:/docs/CommissioningPlan/P1.8 Internal alignment verification]||Day||4||C1||Liquid N2 refill is required in the cleanroom.|| |
| 126 | ||P1.9||[wiki:/docs/CommissioningPlan/P1.9 Internal tip-tilt loop verification]||Day||1||C1||Liquid N2 refill is required in the cleanroom.|| |
| 127 | ||P1.10||[wiki:/docs/CommissioningPlan/P1.10 Motor/light sources functional verification and filter artifacts/defects verification]||Day||1.5||C1||Liquid N2 refill is required in the cleanroom.|| |
135 | | ||P2.0A||[wiki:/docs/CommissioningPlan/P2.0A Installation of the SHARK-NIR at LBT platform - 1]||Day||2(preparation) + 2(lift-off) + 1(contingency)||C2||Crew members' support for the preparation, lift-off, and installation of SHARK-NIR. Crane operator (cleanroom, mountain bay, LBT platform). Safety officer. Working platform installed in front of the Gregorian focal-station SX. Hatch door SX on the UIAP platform removed. Support for the installation of electronics in the LBTO cabinet. Kindly check the installation document, AD3, for more details.|| |
136 | | ||P2.0B||[wiki:/docs/CommissioningPlan/P2.0B Installation of the SHARK-NIR at LBT platform - 2]||Day||2||C2||1-2 crew members' support for the preparation and installation of SHARK-NIR electronics. Safety officer. Kindly check the installation document, AD3, for more details.|| |
137 | | ||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Activating the instrument, basic check, initiate cryostat cool down]||Day||1||C3||Testing the working of the knob (motor/manual) controlling the cooldown. Liquid Nitrogen fill. Vacuum pump.|| |
| 135 | ||P2.0A||[wiki:/docs/CommissioningPlan/P2.0A Installation of SHARK-NIR on LBT platform]||Day||2(preparation) + 2(lift-off) + 1(contingency)||C2||Crew members' support for the preparation, lift-off, and installation of SHARK-NIR. Crane operator (cleanroom, mountain bay, LBT platform). Safety officer. Working platform installed in front of the Gregorian focal-station SX. Hatch door SX on the UIAP platform removed. Support for the installation of electronics in the LBTO cabinet. Kindly check the installation document, AD3, for more details.|| |
| 136 | ||P2.0B||[wiki:/docs/CommissioningPlan/P2.0B Installation of SHARK-NIR electronics on LBT platform]||Day||2||C2||1-2 crew members' support for the preparation and installation of SHARK-NIR electronics. Safety officer. Kindly check the installation document, AD3, for more details.|| |
| 137 | ||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Basic functionality and shutdown procedure test, cryostat cooldown]||Day||1||C3||Testing the working of the knob (motor/manual) controlling the cooldown. Liquid Nitrogen fill. Vacuum pump.|| |